2018-08-07 | Resolucion de Directorio N° 101/2018Added · Updated
The Board of the Central Bank of Bolivia approves a concessional extraordinary credit of Bs94,327,296 to the National Electric Company (ENDE) to finance the "Warnes II Wind Park Construction" project in Santa Cruz. The loan carries a 30-year term with a 5-year grace period on principal, a 1.44% interest rate, and is secured by Non-Negotiable Treasury Bonds. The Central Bank President is authorized to sign the contract with ENDE and the Ministry of Energy, with disbursements required to be completed by March 31, 2021.
SUBJECT: MONETARY OPERATIONS MANAGEMENT – APPROVES CONCESSIONAL EXTRAORDINARY CREDIT IN FAVOR OF THE NATIONAL ELECTRIC COMPANY (ENDE) FOR Bs94,327,296.- PROJECT “WARNES II WIND PARK CONSTRUCTION – SANTA CRUZ”.
That article 6, numeral 9 of the Political Constitution of the State (CPE), establishes that it is the end and function of the State to promote and guarantee the responsible and planned use of natural resources, and to boost their industrialization, through the development and strengthening of the productive base in its different dimensions and levels.
That article 158, paragraph I, numeral 10 and article 322 of the CPE provide that the Plurinational Legislative Assembly will authorize the contracting of public debt when it is demonstrated that there is the capacity to generate income to cover the capital and interest, and that the most advantageous conditions in rates, terms, amounts and other circumstances are technically justified. Public debt will not include obligations that have not been expressly authorized and guaranteed by the Plurinational Legislative Assembly.
That articles 44 and 54 subsections a) and q) of Law No. 1670, of October 31, 1995, of the Central Bank of Bolivia, establish that the highest authority of the BCB is its Board of Directors, which is responsible for defining its policies, specialized regulations of general application and internal rules, as well as for establishing administrative, operational and financial strategies of the BCB, which is why it is empowered to adopt general decisions that may be necessary for the BCB to comply with its functions, powers and competencies recognized by law.
That article 12 of Law No. 614, of December 13, 2014, of the General State Budget – Management 2015, establishes that any authorization established by General State Budget Law for the BCB to grant extraordinary credits, as well as the authorizations to the MEFP to issue and grant Non-Negotiable Treasury Bonds through the General Treasury of the Nation as backing for the referred extraordinary credits, will not require any other legal authorization for their compliance, understanding that they remain in force until the complete execution of the credit.
That article 9, paragraph I of Law No. 769, of December 17, 2015, of the General State Budget – Management 2016, authorizes the BCB to grant an extraordinary credit of up to Bs12,270,161,994.- (Twelve Billion Two Hundred Seventy Million One Hundred Sixty-One Thousand Nine Hundred Ninety-Four 00/100 Bolivianos) under concessional conditions in favor of ENDE, with the object of financing investment projects for generation and transmission in the energy sector, or generation projects that will be executed by its subsidiary or affiliate companies through capital contributions or by ENDE parent company, or by ENDE parent company associated with its affiliate and subsidiary companies. For this purpose, it exempts the BCB from the application of Articles 22 and 23 of Law No. 1670 of October 31, 1995. Likewise, it disposes, in accordance with what is established by article 158, paragraph I, numeral 10 and Article 322 of the CPE, to authorize ENDE to contract the referred credit with the BCB.
That article 9, paragraph III of the aforementioned law, authorizes the MEFP through the TGN, to issue and grant Non-Negotiable Treasury Bonds in favor of the BCB to guarantee the amount of the credit granted at the written request of the lead sector Ministry and jointly with the BCB.
That article 9, paragraph IV of the aforementioned law, establishes that the Ministry of Hydrocarbons and Energy (currently Ministry of Energy), is responsible for the evaluation and monitoring of the execution of the resources of the credit to be granted by the BCB in favor of ENDE.
That article 9, paragraph V of the aforementioned law, determines that ENDE is responsible for the use and destination of the resources to be disbursed by the BCB within the framework of paragraph I of the mentioned article.
That article 9, paragraph VI of the aforementioned law, provides that the MEN through Ministerial Resolution must justify to the BCB that the use and destination of the resources of the credit to be acquired by ENDE are of national priority within the framework of the Economic and Social Development Plan, and that future flows will be used for the payment of the credit.
That the fourth final provision, subsection n) of Law No. 1006, of December 20, 2017, of the General State Budget – Management 2018, establishes that article 12 of Law No. 614 is pending for application.
That article 1 of Supreme Decree No. 3058, of January 22, 2017, provides for the modification of Supreme Decree No. 29894, of February 7, 2009, of Organization of the Executive Branch, to create the MEN. Likewise, in its articles 4, 5 and 6 it determines the attributions of said State Portfolio and the Vice-ministries that form part of its structure.
That the first additional provision of Supreme Decree No. 3070, of February 1, 2017, which modifies Supreme Decree No. 29894 and complements Supreme Decree No. 3058, establishes that for the purposes of the application of Supreme Decree No. 3058, the terms “energy” and/or “energy-related” will encompass the sectors of electrical energy, lithium and nuclear energy, as applicable; and in its third additional provision it disposes that the functions, attributions and competencies of the former Ministry of Hydrocarbons and Energy will be assumed by the Ministry of Hydrocarbons and the MEN, in the hydrocarbons and electrical energy sectors, respectively.
That Ministerial Resolution No. 578, of June 20, 2017, issued by the MEFP, establishes that for Public Enterprises requesting internal public indebtedness, which access extraordinarily to internal credits to be granted by the BCB, the Degree of Concessionality is at least 20% from the date of publication of said Resolution.
That Ministerial Resolution No. 083-18, of May 23, 2018, issued by the MEN, justifies to the BCB that the use and destination of the resources of the credit to be acquired by ENDE are of national priority and resolves: 1) Determine that in accordance with Law No. 769, of December 17, 2015, the project “Warnes II Wind Park Construction – Santa Cruz” will be executed by ENDE, will be partially financed with a credit of Bs94,327,296.00 (Ninety-Four Million Three Hundred Twenty-Seven Thousand Two Hundred Ninety-Six 00/100 Bolivianos), to be requested from the BCB, amount that will be destined to the Project; 2) Approve the technical feasibility of the Project, according to what is stated in the Technical Report ENDE-IT-UPEI-3/12-18 of March 8, 2018 and the Technical Report MEN/MEEA/DGEA/INF-0068/2018 of April 30, 2018; 3) Approve the economic-financial evaluation of the project contained in the financial report ENDE-IF-GDEE-3/1-18 of March 8, 2018, and what is manifested by the Financial Report MEN/DGAA/UFIN/INF-0035/2018 of May 4, 2018, since it has been manifested that ENDE has the payment capacity for the credit to be contracted with the BCB and establishes that the use and destination of the resources of the credit to be contracted by ENDE are of national priority within the framework of the “Patriotic Agenda of the Bicentennial 2025” elevated to the rank of Law by Law No. 650 of January 19, 2015, and of the “Economic and Social Development Plan 2016 – 2020”, approved by Law No. 786 of March 9, 2016; and that the flows contained in the reports mentioned in the preceding paragraph will be used for the payment of the credit to be granted by the BCB in favor of ENDE; and 4) It is established that the MEN through the Vice-ministry of Electricity and Alternative Energies – VMEEA, will authorize ENDE’s disbursement requests to the BCB, based on an evaluation and monitoring report that must be issued for each disbursement, the MEN through the VMEEA will carry out the evaluation and monitoring of the physical and financial execution of the project, ENDE is obliged to send all the information and documentation that is required by the MEN through the VMEEA, for the corresponding evaluation and monitoring.
That the Regulations of the Central Bank of Bolivia for the Approval of Credit to National Strategic Public Enterprises within the framework of the General State Budget, approved by Board Resolution of the BCB No. 019/2016, of February 2, 2016, has the object of regulating the granting of credits by the BCB in favor of the EPNE. Likewise, in its article 8 it establishes that upon receiving the conformity of the FPNE on the financial considerations, the Board of Directors of the BCB through Resolution will approve the granting of the credit, with the favorable vote of two thirds of its members present at the respective meeting and will authorize the President of the BCB to sign the respective contract.
That through Board Resolution No. 007/2018, of March 23, 2018, the Board of Directors of ENDE approves the Investment Plan and the Disbursement Schedule of the resources of the credit to be granted by the BCB for the execution of the Project “Warnes II Wind Park Construction – Santa Cruz”.
That through note ENDE-DGFN-6/55-18, ENDE requests the BCB to grant a concessional extraordinary credit for Bs94,327,296.00 (Eighty-Eight Million Seven Hundred Six Thousand Seventy-Two 00/100 Bolivianos), to finance the Project “Warnes II Wind Park Construction – Santa Cruz”, for which purpose it attaches the documentation established in the Regulations of the Central Bank of Bolivia for the Approval of Credits to National Strategic Public Enterprises within the framework of the General State Budget Laws.
That through note ENDE-DGFN-7/22-18, ENDE remedies the observations made by the BCB clarifying the correct name of the Regulations and attaches the corrected Board Resolution No. 007/2018.
That through notes ENDE-DGFN-6/52-18, ENDE-DGFN-6/53-18 and ENDE-DGFN-6/54-18, ENDE informs the MPD, the MEN and the MEFP, respectively, of the copy of the Board Resolution of ENDE No. 007/2018, of March 23, 2018.
That through note BCB-GOM-SOSP-DCE-CE-2018-149, the BCB communicates to ENDE the conditions approved by the Board of Directors and requests its acceptance.
That through note CITE: ENDE-DGFN-8/4 18, ENDE communicates that its Board of Directors accepts the conditions of the concessional credit approved by the Board of Directors of the BCB.
That through Report BCB-GOM-SOSP-DCE-INF-2018-132, of July 11, 2018, the GOM of the BCB recommends considering the interest rate scenarios proposed for the approval of the financial conditions of the credit requested by ENDE and in case the request is considered favorably, ENDE must open the corresponding disbursement and payment accounts at the BCB through the MEFP.
That through Report BCB-GAL-SANO-DLBCI-INF-2018-208, of July 12, 2018, the GAL of the BCB concludes that the request made by ENDE falls within what is provided for by the current regulations, therefore it is established that ENDE has complied with the presentation of the documentation provided for in article 2 of the Regulations of the Central Bank of Bolivia for the Approval of Credits to National Strategic Public Enterprises within the Framework of the General State Budget Laws, corresponding to the Board of Directors the determination and approval of the financial conditions of the credit, considering the request of ENDE, the recommendations made by the technical area and the degree of concessionality established by the MEFP through Ministerial Resolution for each management. Once the financial conditions are accepted by ENDE, the Highest Authority of the Institution, through Resolution, must approve the request for granting the credit, with the favorable vote of two thirds of the votes of the members present in the meeting and authorize the President of the BCB to sign the Contract as provided in article 8 of the aforementioned Regulations.
Article 1.- Approve within the framework of what is provided in Law No. 769, of December 17, 2015, of the General State Budget – Management 2016 and Law No. 1006, of December 20, 2017, of the General State Budget – Management 2018, of the antecedents and provisions described above, the granting of a concessional extraordinary credit in favor of ENDE, to finance the Project “Warnes II Wind Park Construction – Santa Cruz”, under the following terms and conditions:
| Concept | Detail |
|---|---|
| Currency: | Bolivianos. |
| Total Credit Amount: | Bs94,327,296.00 (Ninety-Four Million Three Hundred Twenty-Seven Thousand Two Hundred Ninety-Six 00/100 Bolivianos). |
| Term: | 30 years from the first disbursement. |
| Grace Period on Principal: | 5 years. |
| Interest Rate: | 1.44% (one point four four percent). |
| Disbursement Deadline: | March 31, 2021. |
| Payment Plan: | Annual. |
| Guarantees: | Non-Negotiable Treasury Bonds. |
Article 2.- Authorize the Acting President of the BCB to sign the contract with ENDE and the MEN under the terms of this Resolution.
Article 3.- The Presidency and the General Management are in charge of the execution and compliance of this Resolution.
La Paz, August 7, 2018
Pablo Ramos Sánchez
Abraham Pérez Alandia
Gabriel Herbas Camacho
Luis Baudoin Olea
Ronald Poló Rivero
Sergio Velarde Vera
More like this from BCB