The Central Bank of the Republic of Azerbaijan issued Resolution No. 04/1 to establish minimum requirements for operational risk management across all banks and foreign bank branches. The regulation mandates a comprehensive risk management system integrating defined policies, assessment tools like RCSA and key indicators, continuous monitoring via management information systems, and robust mitigation strategies for outsourcing and ICT risks. It further requires institutions to maintain a historical incident database for empirical forecasting, develop stress-tested business continuity plans to ensure operational resilience during disruptions, and submit regular risk reports to supervisory and management boards.
CBAR published 1 document in the last 30 days — get each new one by email the day it lands.
‘Approved’
Central Bank of the Republic of Azerbaijan
Resolution № 04/1
‘28’ January 2025
Regulation on operational risk management in banks
General provisions
1.1. This Regulation has been developed in accordance with Article 34.5 of the Law of
the Republic of Azerbaijan ‘on Banks’ (hereinafter – the Law) and establishes minimum requirements for the operational risk management in banks, as well as in local branches of foreign banks (hereinafter – banks).
1.2. The organizational structure of the operational risk management in bank sis
regulated with the ‘Corporate governance standards in banks’ approved by Resolution No 41/1 of the Central Bank of the Republic of Azerbaijan (hereinafter – the Central Bank) dated 28 August 2023.
Definitions
2.1. The definitions used in this Regulation bear the following meanings:
2.1.1. operational risk – the risk of loss arising from inadequate or failed internal
processes, people, systems, or external events.
2.1.2. incident – an event that causes the disruption or interruption of bank’s critical
operations.
2.1.3. total loss – the damage incurred by the bank resulting from a risk event.
2.1.4. recoverable amount – the amount paid or refunded by the liable party and/or a
third party for the total loss.
2.1.5. outsourced service – a service where certain activity/ies is/are continuously
performed by a third party (whether it belongs to the bank’s corporate group) based on an agreement between the parties.
2.1.6. market approach – the valuation of an asset based on a comparison with identical
or similar assets available in the market.
2.1.7. cost approach – the valuation of an asset based on the principle that its cost
should not exceed the expense a buyer would incur to acquire (purchase, construct, etc.) an asset of equal utility.
2.1.8. operational resilience – bank’s ability to deliver critical operations during an
incident.
2.1.9. critical operations – operations, processes, and services essential for the bank’s
business continuity.
2.2. Other definitions used in this Regulation bear the meanings as defined in the Civil
Code of the Republic of Azerbaijan, the ‘Corporate governance standards in banks,’ and other legal acts regulating financial markets.
The operational risk management system
3.1. The bank establishes an operational risk management system, adequate for the
type, volume, and nature of its operations, the environment it operates in, and its risk profile.
3.2. The operational risk management system is integrated into the bank’s overall risk
management process, covering all areas of its activities, including business lines, products, services, processes, and systems.
3.3. The bank’s Supervisory Board ensures the establishment and assessment of the
effectiveness of the bank’s operational risk management system.
3.4. The bank’s Supervisory Board reviews at least once a year the adequacy of the
operational risk management system in addressing risks arising from new products, services, processes, and systems, and external environmental changes and other factors, as well as findings of reviews conducted by internal audit, external audit, and other specialized third parties and makes relevant decisions accordingly.
3.5. The operational risk management system should be designed in alignment with the
bank’s operational policies and should cover at least:
3.5.1. operational risk management policies and procedures.
3.5.2. tools for identifying and assessing operational risks.
3.5.3. operational risk monitoring and reporting.
3.5.4. operational risk control and risk mitigation methods.
3.5.5. bank’s operational resilience and business continuity plan.
3.6. The operational risk management system applies to all structural units of the bank,
both domestic and international operational units, as well as its subsidiary entities.
Operational risk management policies and procedures
4.1. The operational risk management policy is developed in accordance with the
bank's business strategy and risk appetite. In addition to the requirements specified in the ‘Corporate governance standards for banks’ regarding risk management policies, the operational risk management policy should include at least the following:
4.1.1. types of operational risks inherent to the bank in relation to occurred and
potential incidents.
4.1.2. procedures for utilizing outsourced services.
4.1.3. limits on operational risks the bank may be directly or indirectly exposed to,
including loss limits, risk mitigation methods, and other related matters, in line with the bank's risk-taking capacity and risk appetite.
4.1.4. fundamental principles of the Management Information System (hereinafter – the
MIS) used in monitoring and reporting processes.
4.1.5. the scope and use of operational risk information, including potential loss
information and scenario analyses.
4.1.6. creating a favorable environment for external auditors to assess operational risks.
4.1.7. reviewing and updating the policy as needed if the growth dynamics of bank's
assets exceed the sector's asset growth dynamics.
4.2. The bank develops internal rules for managing operational risks in accordance with
the nature of its activities and the scope of its operations. These rules comprehensively
regulate bank's risk-generating activities and the process of operational risk management, serving as a guiding framework for implementing the operational risk policy. Internal rules on operational risks should be aligned with other policies and internal rules.
4.3. To identify and assess potential operational risks associated with new products,
services, activities, processes, and systems internal rules should cover at least:
4.3.1. operational risks inherent to new products, services, activities, processes, and
systems.
4.3.2. changes in the overall operational risk profile (including risks related to available
products and activities), risk appetite, including risk limits, and risk-taking capacity.
4.3.3. due diligence, risk management, and mitigation strategies.
4.3.4. residual risk after implementing all measures to identify, measure, and mitigate
risks.
4.3.5. measuring, monitoring, and managing risks associated with new products,
services, activities, processes, and systems.
4.4. Internal rules should designate the structural unit responsible for centralized
oversight of operational risk management, and define its authority, reporting structure, reporting procedures, and interactions with other structural units within the bank.
4.5. The bank should review its operational risk policy and internal rules at least once a
year and make necessary amendments as required.
5. Tools for identifying and assessing operational risks
5.1. Each bank identifies and assesses operational risks associated with its products,
activities, processes, and systems.
5.2. To effectively identify operational risks, the bank should consider both internal
(organizational structure, nature of operations, staff capacity, organizational changes, employee turnover, etc.) and external factors (changes in the economic environment and banking sector, technological innovations, etc.).
5.3. The bank utilizes at least the following tools to identify and assess operational
risks:
5.3.1. audit findings: information from internal and external audits is used to identify
operational risks.
5.3.2. collection and analysis of operational risk incident information: a database is
created and analyzed to assess the scale of operational risks and the effectiveness of internal controls (the collection and reporting of operational risk event information are regulated under Part 9 of this Regulation).
5.3.3. operational risk self-assessment: the Risk and Control Self-Assessment (RCSA)
process is conducted to identify potential threats, risk-sensitive areas, and evaluate control effectiveness on operations arising from activity directions of the bank and is conducted at least once a year for critical operational units and at least once every two years for the bank.
5.3.4. process mapping: during RCSA various, including interconnected risks are
identified with the process mapping, and vulnerabilities in risk management and control functions are detected and analyzed. The process mapping is developed considering the opinion of the structural unit responsible for risk management.
5.3.5. heat map: a heat map is prepared based on RCSA results, operational risk
incident information, and other sources to visualize encountered risks, prioritizes them, and
an action plan is developed to mitigate risks. A sample heat map is provided in Annex 1 to this Regulation.
5.3.6. Key Risk and Performance Indicators: Key Risk Indicators (KRIs) and Key
Performance Indicators (KPIs) analyze major risks the bank is exposed to. The KRI is the tool that measures the impact of major risks and KPIs provide information on operational gaps, errors, and potential losses in systems and processes (both indicators serve as early warning tools for risk limit breaches).
5.3.7. scenario analysis is the process which identifies and assesses potential impacts of
potential operational risk incidents based on the judgement of experts from business units and risk specialists (this analysis may use the information from loss databases, selfassessments (RCSA, KRI, KPI), monitoring results, and other risk information).
5.3.8. comparative analysis: results of different risk assessment tools are compared for
a comprehensive understanding of the bank’s risk profile (e.g., the frequency and impact of observed risk events from the loss database can be compared with RCSA results to measure the effectiveness of the self-assessment process).
5.4. Using the data collected through the risk assessment tools listed in Item 5.3 herein,
the bank calculates its exposure to operational risk through internally developed models.
6. Operational risk monitoring and reporting
6.1. A bank should have written procedures and an information system for monitoring
operational risks that are adequate for its risk profile and business activities. For monitoring of operational risks, at least:
6.1.1. an early warning mechanism is established, and trends in KRIs are regularly
monitored.
6.1.2. trends in risk events recorded in the operational risk events database are tracked.
6.1.3. the implementation status of the action plan developed for mitigating operational
risks is tracked.
6.1.4. risk events exceeding the limit set by the bank for losses, in accordance with subitem 4.1.3 of this Regulation, are investigated.
6.1.5. back testing (comparison of projected losses with actual results) is conducted for
losses forecasted in previous periods.
6.1.6. external events and their potential impact on operational risks are assessed.
6.1.7. operational risks arising from outsourcing is monitored.
6.2. The Management Board should ensure that employees responsible for monitoring
operational risks are independent of the operational units they oversee (e.g., a monitoring employee should not work in the operational unit being monitored, there should be no conflict of interest regarding monitoring results, and the monitoring report should be unbiased and objective).
6.3. The bank should have a reporting mechanism that supports the effective
management of operational risks for the Supervisory Board, Risk Management Committee, Management Board, and relevant operational units. The report should include at least:
6.3.1. information on the bank's risk appetite and breaches of risk limits.
6.3.2. information on internal operational risk events and related losses during the
reporting period.
6.3.3. events that may have a potential impact on the bank and its capital, including
external incidents and regulatory changes.
6.3.4. causes of operational risk incidents and measures taken to mitigate them.
6.3.5. information on high-risk areas related to operational risks.
6.3.6. operational risks identified by the bank, monitoring results, verification of the
process for recording operational risk incidents in the database, and risks identified by external auditors and the Central Bank.
6.4. to ensure the effectiveness of operational risk monitoring and risk reporting, an
MIS is implemented, enabling at least:
6.4.1. identification, assessment, management, and control of daily risks.
6.4.2. verification of compliance with established rules and limits.
6.4.3. monitoring trends in risk indicators.
6.4.4. preparation of reports in accordance with legal acts and internal policies.
6.5. The MIS should be capable of tracking risk limits and notifying the Management
Board and other relevant users when predefined thresholds are reached.
6.6. Reports generated by the MIS should be accessible to members of the Supervisory
Board, Management Board, Risk Management Committee, and employees responsible for risk management.
6.7. The bank determines the frequency of monitoring and reporting based on the scale
and nature of risks arising from its activities and changes in financial markets.
6.8. In cases of external events and threats that may impact bank's operations (e.g.,
martial law, state of emergency, pandemic, terrorism, etc.), an additional report is prepared and submitted to the Supervisory Board, Risk Management Committee, and Management Board, in addition to periodic operational risk reports.
6.9. The information covered in operational risk reporting should be regularly analyzed
to improve the bank's strategy, policies, and procedures.
7. Operational risk control and risk mitigation
7.1. The bank should have a strong control environment that utilizes policies,
procedures, systems, internal controls, and strategies for risk mitigation and/or transfer.
7.2. Internal control oversees efficiency of operations, minimization of human errors,
security of assets, guarantees the completeness, timeliness, and reliability of financial reports and other information, and ensures compliance with legal and regulatory requirements.
7.3. Control processes cover the bank's operational resilience both under normal
conditions and in the event of incidents and necessary corrective measures.
7.4. Effective internal control consists of risk assessment, control, information and
communication, and monitoring, all of which are integral to the risk management process.
7.5. The control process should be structured in accordance with the legislation,
regulations of the Central Bank, and the bank's internal policy. To assess the adequacy of the control process to the bank's policy, at least the following should be considered:
7.5.1. regular monitoring by the Management Board of actions taken to achieve
established objectives.
7.5.2. oversight by the Management Board on the implementation of corrective actions
plans designed to address identified violations.
7.5.3. reviewing the preparation, approval, and submission of internal reports to ensure
they are completed within the deadline.
7.5.4. ensuring accountability and regular monitoring of deviations from limits (e.g.,
risk limits, authority thresholds) and/or the bank’s policy.
7.6. To establish an effective control environment, the bank should clearly segregate
duties and responsibilities, as well as enforce dual control (the ‘four-eyes’ principle). In addition to segregation of duties and dual control, the bank should at least:
7.6.1. conduct intensive monitoring of established limits and investigate any breaches.
7.6.2. ensure the security of bank’s assets and database usage (e.g., access permits,
necessary infrastructure, authentication, etc.).
7.6.3. recruit qualified personnel and provide training opportunities to ensure
specialization across all areas of the bank’s operations.
7.6.4. implement procedures to identify business areas or products generating higherthan-expected profits and analyze reasons behind their profitability (e.g., if the bank earns
unusually high profits from a low-risk, low-expected-return activity, it should be investigated to find out whether this is due to regulatory violations or internal control weaknesses).
7.6.5. regularly review and reconcile transactions and accounts.
7.6.6. establish a substitution policy to address potential disruptions in authority
execution when employees are unable to perform their duties for two weeks or more due to leave, illness, or other reasons.
7.6.7. develop an internal risk culture through training programs and enhance
communication on risk management within the bank.
7.7. Given the significant impact of information and communication technologies (ICT)
on the efficiency of internal control, the bank should adopt a unified approach to identifying, measuring, monitoring, and managing ICT risks. The management of ICT risks in banks is regulated by the ‘Information security requirements for supervised entities in financial markets’ approved by Decision No. 14/2 of the Central Bank dated 28 March 2024.
7.8. The bank may utilize outsourcing, considering the opinion of the structural unit
responsible for the risk management function. The bank remains responsible for any risks arising from outsourcing. When using outsourcing, the bank should ensure at least the following for effective management of operational risks associated with outsourcing:
7.8.1. establishing an internal policy for managing risks associated with outsourcing.
7.8.2. procedures for conducting operations through outsourcing.
7.8.3. a selection process for potential service providers.
7.8.4. ensuring that agreements with service providers explicitly outline
responsibilities, authority distribution, and confidentiality of information, including banking secrecy.
7.8.5. procedures for monitoring and managing risks related to external service
providers, including evaluating their financial stability.
7.8.6. creating effective control environment in the bank and at the service provider.
7.8.7. a business continuity plan for outsourced activities.
7.9. When outsourcing banking activities, information technology, or information
security services, the bank should submit details regarding the outsourced service and the service provider (including the provider's business scope and experience in the relevant
service area) to the Central Bank along with the signed agreement within five (5) business days.
7.10. If the bank is unable to manage risks arising from outsourcing but considers
discontinuing the outsourced service impractical, it may transfer its exposure to such risks to a third party through insurance or other risk mitigation mechanisms.
8. Bank’s operational resilience and business continuity plan
8.1. In the case of an incident, the bank should have operational resilience for the
execution of critical operations. Operational resilience is built on incident response measures, situational adaptation, recovery plans, and practices.
8.2. In the event of business disruptions, in martial law and emergency situations,
including natural disasters, epidemics and pandemics, terrorism, and other emergencies, the bank should develop as part of the bank's overall emergency plan a business continuity plan to manage operational risks and ensure business continuity to limit losses and ensure the continuity of its operations.
8.3. To ensure operational resilience, the bank should identify at least its critical
operations, conduct stress tests in various scenarios, form a business continuity plan, and effectively manage dependencies on third parties.
8.4. The business continuity plan is developed in accordance with the size, business
direction, operational volume, and complexity of the bank, and is based on scenarios to which the bank is vulnerable. The business continuity plan should at least cover:
8.4.1. analysis of the impact of the scenarios listed in section 8.2 herein on business
operations.
8.4.2. business recovery strategy.
8.4.3. segregation of roles and responsibilities in emergencies.
8.4.4. organization of communication.
8.4.5. recovery procedures.
8.5. To ensure the effective implementation of the Business Continuity Plan, the bank
should provide training and awareness programs for employees, test the plan at least once a year, and report test results and any necessary changes to the bank's Supervisory Board.
9. Collection and reporting of operational risk events related information
9.1. The bank should collect information on operational risk incidents to verify its
operational risk management system and conduct empirical (experience-based) risk forecasting related to losses.
9.2. The operational risk incident database should include information directly related
to bank’s current business activities, technological processes, and risk management procedures. To achieve this, the bank should have written procedures for identifying and collecting information on operational risk incidents.
9.3. To adequately measure operational risks using internal models, the bank should
maintain an operational risk incident database covering at least the past three (3) years. This database should facilitate the identification of risk incidents, support for operational units in minimizing or eliminating risks through action plans, statistical analysis of risk types, causes, frequency, and impact for forecasting and prioritization.
9.4. In forming the operational risk incident database, at least the following should be
ensured:
9.4.1. the information on operational risk incidents is collected in accordance with the
business areas and risk events specified in Annexes 2 and 3, and the impact of losses resulting from operational risks is classified based on the example provided in Annex 6.
9.4.2. key activities and risks across the bank's entire service network (branches,
departments, etc.).
9.4.3. the operational risk incident database includes at least the indicators specified in
Annex 4 of this Regulation.
9.4.4. operational risk incidents that have resulted or have the potential to result in
credit and market risks are recorded in the database with a special note.
9.4.5. operational risks arising from outsourced services are included in the database.
9.4.6. when utilizing the operational risk incident database, the date when the loss was
identified (if a monetary loss occurred), or the date when the operational risk incident took place (if no monetary loss occurred) is taken as the basis.
9.4.7. interrelated incidents and losses are grouped and reflected as a single entry in the
database.
9.4.8. if an operational risk incident affects multiple business areas, the resulting loss is
recorded in the database proportionally across relevant business areas.
9.4.9. total loss recorded in the operational risk incident database is calculated with the
market and/or cost approach. The following requirements should be met in the loss calculation:
9.4.9.1. direct costs recognized in the income statement related to the operational risk
incident (e.g., asset impairments and write-offs), indirect costs (e.g., legal expenses, payments to consultants or providers), and restoration costs incurred to restore the situation to its pre-incident state.
9.4.9.2. maintenance costs for land, buildings, and equipment, insurance premiums are
not considered in the total loss calculation.
9.5. The bank collects quarterly information on operational risk incidents related to its
subsidiary banks. Based on this information, the bank establishes a separate database for subsidiary banks in accordance with Annex 4 of this Regulation.
9.6. To facilitate the collection of operational risk incident information, the bank should
designate an operational risk coordinator in each structural unit. The coordinator:
9.6.1. investigates and records the risk incident using the single format established by
the bank.
9.6.2. obtains approval from the head of the structural unit for the recorded risk
incident.
9.6.3. submits the approved information and related documents to the risk
management unit within two (2) business days from the date of identification of the incident, as per sub-item 9.6.1 of this Regulation. The coordinator immediately reports the incident to the risk management unit if:
9.6.3.1. the risk incident results in a breach of risk limits.
9.6.3.2. the risk incident could lead to binding instructions against the bank, including
sanctions or enforcement measures.
9.6.3.3. cases of internal or external fraud occur.
9.6.3.4. the monetary loss caused by the risk incident exceeds the threshold limit set by
the bank in accordance with sub-item 4.1.3 of this Regulation.
9.7. To ensure the accuracy and completeness of the information, operational risk
incident records are reviewed at least quarterly. In case of any changes, the risk management unit is notified accordingly.
9.8. After the information on the risk incident is submitted, the operational risk
responsible employee in the bank’s Risk Management Unit investigates and confirms the incident within three (3) business days and registers it in the bank’s database.
9.9. The bank should submit information on the following incidents to the Central Bank
as per Annex 5 of this Regulation, no later than fifteen calendar days after the end of each quarter:
9.9.1. incidents where total loss amount is AZN100,000 (one hundred thousand) or
more per incident.
9.9.2. incidents that have occurred frequently (10 or more times within the last 12
months).
9.9.3. incidents where potential loss is AZN100,000 (one hundred thousand) or more.
9.10. If the Central Bank requests additional information or documents related to
operational risk incidents for supervisory purposes, the bank should provide the relevant information and documents within the deadline.
Annex 1
to the ‘Regulation on operational risk management in banks’ Sample heat map Impact Very high (5) 5 10 15 20 25 High (4) 4 8 12 16 20 Medium (3) 3 6 9 12 15 Low (2) 2 4 6 8 10 Very low (1) 1 2 3 4 5 Very low (1) Low (2) Medium (3) High (4) Very high (5) Probability Very high High Medium Low Very low
Annex 2 to the ‘Regulation on operational risk management in banks’
BREAKDOWN OF BUSINESS AREAS
Business areas Classification code Description Corporate finance BS1 Provide financial advisory services to businesses for long-term and strategic operations, and increasing liquidity, as well as investment services (operations) with securities and derivative financial instruments in accordance with the scope and procedure stipulated in the Law of the Republic of Azerbaijan ‘on the Securities Market.’ Asset management BS2 Provide investment services (operations) with securities and derivative financial instruments to individuals in accordance with the scope and procedure stipulated in the Law of the Republic of Azerbaijan ‘on the Securities Market.’ Consumer banking BS3 Issue loans to individuals for purposes unrelated to entrepreneurship or professional activities, including real estate loans, attract deposits from individuals, issue payment instruments, and provide other services. Commercial banking BS4 Provide business financing, including project financing, export financing, factoring, leasing, guarantees, and services unrelated to other business areas Payment systems and settlements BS5 Payments, money transfers, clearing and settlements Agency services BS6 Financial agent services
Annex 3 to the ‘Regulation on operational risk management in banks’
BREAKDOWN OF RISK INCIDENTS
Type of operational risk
Risk event category
(Level 1)
Definition
Risk event category
(Level 2)
Risk event
(Level 3)
(Sample)
1
Processes
Work relations and workplace safety (R1)
Losses arising from violations of labor, health, or safety laws and/or regulations, as well as from actions contrary to agreements, compensation for healthrelated damages, or unlawful conduct and discrimination against employees. Employee relations (R1.1) Compensation and issues related to termination of labor agreements Strikes within the workforce Safe environment (R1.2) Occupational Safety Incidents related to employee health and safety Compensation for employees Unlawful conduct and discrimination (R1.3) All types of discrimination and unlawful actions Customers, products, and business relations (R2) Losses arising from the unintentional or negligent failure to fulfill professional obligations to certain customers (including reliability and compliance requirements), as well as from the nature and design of the bank product. Violations related to compliance, data disclosure and reliability (R2.1) Violation of fiduciary duties / Violation of rules Issues related to compliance / disclosure of information (‘Know Your Customer’ principles, etc.) Violations regarding the disclosure of customer information Breach of confidentiality Aggressive sales practices Inflation of accounts Misuse of confidential information Violation of lending obligations Unprofessional business or market relations Illegal trade / market relations Market manipulation Insider trading (conducted from the bank's account) 1 The bank may increase the samples related to Level 3 risk incidents.
Processes
(R2.2) Unlicensed activities
Money laundering activities
Defects in products (R2.3)
Defects in products
Model errors
Violations related to customer selection, sponsorship, and the volume of loan claims (R2.4) Failure to conduct customer due diligence according to instructions Violation of customer limits Advisory service (R2.5) Disputes related to the provision of advisory services Execution, delivery, and process management (R3) Losses arising from incorrect execution of operations, inadequate process management, or relationships with business partners and suppliers Work, execution, and attendance (R3.1) Information asymmetry Errors in data entry, implementation, or upload Fail the deadline or to fulfill the obligation Mismanagement of the model/system Accounting error / error in company’s details Delivery error Error in collateral managing Other job violations Monitoring and reporting (R3.2) Failure to comply with the reporting requirements set by legislation Inappropriate external reporting (resulting in monetary loss) Customer onboarding and documentation (R3.3) Incomplete customer consent / refusal documents Incomplete / missing legal documents Customer account management (R3.4) Unauthorized / unapproved access to accounts Incorrect customer registration (resulting in monetary loss) Loss or damage to customer assets due to negligence Trade partners (R3.5) Failure of non-customer counterparties to properly fulfill their obligations
Disputes with non-customer counterparties
Vendors and providers (R3.6)
External services
Disputes with vendors
Human
Internal fraud (R4)
Losses arising from fraud involving at least one bank employee, embezzlement of bank property, or violations of legislation, as well as bank's internal policies and rules Unauthorized operations (R4.1) Unauthorized transactions (resulting in monetary loss) Undeclared and unnotified transactions (deliberately) Incorrect reporting of financial indicators (deliberately) Embezzlement and fraud (R4.2) Fraud / credit fraud / worthless (fake) deposits Theft / robbery / misappropriation of funds / pillage Asset misappropriation Willful destruction of assets Forgery Writing a non-existent check Customer account takeover / identity impersonation Abusive tax transactions / (deliberate) tax evasion Bribery / illegal payment Insider trading (not conducted from the bank's account) External fraud (R5) Losses arising from fraud, embezzlement of bank property, or other illegal acts committed by a third party Embezzlement and fraud (R5.1) Theft / robbery / misappropriation or waste / pillage Fraud Issuing a worthless check System security (R5.2) Cyberattack Data theft System Operations disruption and system errors (R6) Losses arising from disruption of operations or system errors Systems (R6.1) Equipment Software Communication Utility Outages / Disruptions External events Damage to physical assets (R7) Loss or damage to physical assets due to natural disasters or other events Natural disasters and other events (R7.1) Losses caused by natural disasters Losses due to external factors (Vandalism, Terrorism)
Annex 4 to the ‘Regulation on operational risk management in banks’
OPERATIONAL RISK INCIDENT DATABASE
№ Information about damages
Registration date (d.m.y)
Registration code2
The employee who enters information into the database
Structural unit, the risk incident occurred in
Employee who provided the information (coordinator)
Date and time of the risk incident (d.m.y.)
Date and time the risk incident was found out (d.m.y.)
Employee who found out the risk incident
Description of the risk incident
Cause of the risk incident
Frequency rate
Impact rate
Business area code
Bank product
Risk incident category code (Level 1)
Risk incident category code (Level 2)
Risk incident (Level 3)
Damage impact category
Total loss amount, in thousand manats
Potential loss amount
Recovery date (d.m.y.)
2 For instance, in the event of an external fraud in the payment systems and settlements business area the registration code - BS5R5.1
Recovered amount (in thousand manats)
22.1. Part of loss recovered through insurance (in thousand manats)
Date of actions on elimination of the risk incident (d.m.y.)
Description of actions on elimination of the risk incident
Structural unit responsible for the actions on elimination of the risk incident
Status of execution of the actions on elimination of the risk incident
Date of recent change (d.m.y.) and brief description of the change
Note: Sections 23-26 of this Annex are filled out for losses exceeding the limit set by the bank's internal rules.
Annex 5 to the ‘Regulation on operational risk management in banks’
GENERAL INCIDENT REPORT
Bank name: License number:
Reporting period:
Date of completion of the report:
Structural unit responsible for the report:
Person responsible for the report:
Firs, last, middle names:
Position:
E-mail address:
Phone number:
Person who compiled the report:
Firs, last, middle names:
Position:
E-mail address:
Phone number:
Business areas
Indicators
Types of risk incidents TOTAL
Work relations and workspace safety
Customers, products, and business relations
Execution, delivery, and process management
Internal fraud
External fraud
Disruption of operations and system errors
Damage to physical assets
Corporate finance
Number of incidents occurred
Frequency of incidents
Largest amount on the incidents occurred
Total loss
Net loss (Total loss-
recovered amount)
Potential loss amount
Asset management
Number of incidents occurred
Frequency of incidents
Largest amount on the incidents occurred
Total loss
Net loss (Total lossrecovered amount)
Potential loss amount
Consumer banking
Number of incidents occurred
Frequency of incidents
Largest amount on the incidents occurred
Total loss
Net loss (Total lossrecovered amount)
Potential loss amount
Commercial banking
Number of incidents occurred
Frequency of incidents
Largest amount on the incidents occurred
Total loss
Net loss (Total lossrecovered amount)
Potential loss amount
Payment systems and
Number of incidents occurred
settlements Frequency of incidents
Largest amount on the incidents occurred
Total loss
Net loss (Total lossrecovered amount)
Potential loss amount
Agency services
Number of incidents occurred
Frequency of incidents
Largest amount on the incidents occurred
Total loss
Net loss (Total lossrecovered amount)
Potential loss amount
On business areas
(TOTAL)
Number of incidents occurred
Frequency of incidents
Largest amount on the incidents occurred
Total loss
Net loss (Total lossrecovered amount)
Potential loss amount
Annex 6 to the ‘Regulation on operational risk management in banks’
Sample damage impact categories
Category Description Scope
Legal responsibility Mediation and other pre-trial dispute resolution methods, legal costs related to court decisions, as well as other legal expenses
Loss of resources Losses incurred due to a third party's failure to fulfill its obligations to the bank resulting from operational risk for which the bank is responsible
Note from RegAlert. AI assistants can read this document in full, and search 70,000+ more, through the RegAlert MCP connector (https://mcp.regalert.today/mcp). Free with an account. How to connect ChatGPT, Claude or Cursor.
Source: Central Bank of Azerbaijan — original document · Summary generated with machine assistance and reviewed before publication; the authoritative text is the regulator's original document. How RegAlert works
More like this from CBAR
CBAR published 1 document in the last 30 days. We email you each new one the day it's published.