Guidance · BOG · 6 Nov 2026
Issuers of asset-referenced tokens (ARTs) must maintain an operational risk management and operational resilience framework, with the Management Board approving strategies, policies and procedures including risk appetite and risk tolerance for disruption of critical or important functions. Entities must identify critical activities and map people, technology, processes, data, facilities and third parties, subject the framework to regular review by internal or external auditors, and establish an ICT risk management framework under Regulation (EU) 2022/2554. Before entering third-party agreements for reserve asset management, investment, custody or ART distribution, entities must approve and regularly update an operational reliability policy, conduct risk-based due diligence, and ensure documented exit plans.
THE EXECUTIVE COMMITTEE
Meeting 262/06.11.2026
Subject 1:
Adoption of the Guidelines of the European Banking Authority on the minimum content of governance arrangements for issuers of asset-referenced tokens (EBA/GL/2024/06)
THE EXECUTIVE COMMITTEE OF THE BANK OF GREECE, having taken into account:
a) Articles 28 and 55A of the Statute of the Bank of Greece (A’ 298/1927),
b) the provisions of Part C of Law 5193/2025 “Strengthening of the capital market and other provisions” (A’ 56), and in particular Articles 99 and 115 thereof,
c) Regulation (EU) 2023/1114 of the European Parliament and of the Council of 31 May 2023 on markets in crypto-assets and amending Regulations (EU) No 1093/2010 and (EU) No 1095/2010 and Directives 2013/36/EU and (EU) 2019/1937 (L 150/40),
d) Regulation (EU) No 1093/2010 of the European Parliament and of the Council of 24 November 2010 establishing a European Supervisory Authority (European Banking Authority), amending Decision No 716/2009/EC and repealing Commission Decision 2009/78/EC (EU L 331/12, 15.12.2010), and in particular Article 16 thereof,
e) Regulation (EU) 2022/2554 of the European Parliament and of the Council of 14 December 2022 on digital operational resilience for the financial sector and amending Regulations (EC) No 1060/2009, (EU) No 648/2012, (EU) No 600/2014, (EU) No 909/2014 and (EU) 2016/1011 (L 333/1),
f) Executive Committee Act (ECA) 243/2/07.07.2025 of the Bank of Greece “Internal governance framework - Adoption of the guidelines of the European Banking Authority on internal governance (EBA/GL/2021/05) - Repeal of PΔ/TE 2577/9.3.2006 ‘Framework of operating principles and evaluation criteria for the organisation and the Systems
THE EXECUTIVE COMMITTEE
of Internal Control of credit and financial institutions and the relevant competences of their management bodies’ (A’ 59)” (B’ 3658),
g) ECA 164/2/13.12.2019 “Terms and conditions for: a) the granting of a licence for the establishment and operation of payment institutions and electronic money institutions and the registration of account information service providers in Greece, b) the acquisition, increase or disposal of a qualifying holding, c) the assumption of the position of member of the Board of Directors and others, d) the determination of the minimum monetary amount of professional liability insurance or other comparable guarantee, e) the supervisory rules, f) the keeping of the register of Article 14 of Law 4537/2018 and g) the determination of the procedure for the participation of payment institutions and electronic money institutions in recognised payment systems” (B’ 4981), and in particular Section 2 of Chapter VIII and Section 2 of Chapter X thereof,
h) the Guidelines of the European Banking Authority (EBA) on the minimum content of governance arrangements for issuers of asset-referenced tokens (EBA/GL/2024/06),
i) that the provisions hereof do not concern an administrative procedure for which there is an obligation of registration in the EMΔΔ-MITOS,
j) that the provisions hereof do not cause expenditure against the state budget,
DECIDES
to adopt the EBA Guidelines on the minimum content of governance arrangements for issuers of asset-referenced tokens (ARTs) (EBA/GL/2024/06).
1. This Act incorporates into the Greek legal order the EBA Guidelines on the minimum content of governance arrangements for issuers of ARTs (EBA/GL/2024/06), which were issued pursuant to paragraph 13 of Article 34 of Regulation (EU) 2023/1114, to the extent that they concern issuers of ARTs subject to the competence of the Bank of Greece by virtue of Article 99 of Law 5193/2025 and to the extent that their arrangements are not already covered by the existing legislation. In particular, this Act specifies the minimum content of governance arrangements for issuers of ARTs, in particular as regards operational risk management, operational resilience and business continuity management.
THE EXECUTIVE COMMITTEE
2. The provisions hereof apply, in addition to the requirements of ECA 243/2/07.07.2025 and Regulation (EU) 2022/2554, to credit institutions established in Greece, payment institutions established in Greece and electronic money institutions established in Greece (hereinafter for the purposes of this Act “entities”) that intend to issue ARTs.
3. Unless otherwise provided herein, the terms used and defined in Regulation (EU) 2023/1114, Regulation (EU) 2022/2554, Law 4261/2014, ECA 243/2/07.07.2025 and ECA 224/1/21.12.2023 have the same meaning in this Act. In addition, for the purposes of this Act the following definitions apply:
a) operational resilience: the ability of an issuer of ARTs to provide critical or important functions amid operational disruptions,
b) operational risk: operational risk as defined in point 52 of paragraph 1 of Article 4 of Regulation (EU) No 575/2013.
4. Entities take into account the principle of proportionality in order to ensure that governance arrangements are consistent with their individual risk profile and that of the group to which they may belong, as the case may be, proportionate to their size and internal organisation, relevant to their business model, appropriate to the nature, scale and complexity of their activities and sufficient for the effective achievement of the objectives of the relevant regulatory requirements.
5. For the purposes of applying the principle of proportionality and ensuring the appropriate application of the governance requirements of Regulation (EU) 2023/1114, entities must take into account the following criteria:
a) their size in relation to the total balance sheet,
b) their legal form,
c) whether they are listed on a regulated market,
d) the classification of the ARTs issued as significant or non-significant in accordance with Articles 43 and 44 and Articles 56 and 57 of Regulation (EU) 2023/1114,
e) the specificities, volume and number of ARTs issued,
f) whether the ARTs issued have been admitted to trading,
g) the consensus mechanism used for the issuance and validation of the ARTs,
h) the nature and complexity of all business activities,
THE EXECUTIVE COMMITTEE
i) the type of authorised activities and services provided,
j) whether cross-border activities are carried out and the scale of activities in each jurisdiction,
k) the size of the reserve of assets,
l) the type and complexity of the assets to which the ARTs refer,
m) whether the holders of ARTs are retail holders or not,
n) the use of third-party service providers,
o) the distribution channels used, including those provided by third-party service providers, and
p) the existing information systems, including business continuity measures and the use of third-party information systems, as provided for in point (h) of the second subparagraph of paragraph 5 of Article 34 of Regulation (EU) 2023/1114.
6. Entities must have an adequate operational risk management framework and operational resilience framework. These frameworks include effective policies and procedures to achieve the following objectives:
a) identification, assessment, evaluation, monitoring, reporting and mitigation of operational risk in a timely manner, and
b) identification of threats and potential failures and protection of entities from such threats and failures, response and adaptation, as well as recovery and drawing lessons from disruption incidents with the aim of minimising their impact on the provision of critical or important functions1 .
7. The Management Board of entities must, as part of the risk management framework, approve strategies, policies and procedures for the management of operational risk and operational resilience, including the risk appetite for the operational risk framework and the risk tolerance in the event of disruption of critical or important functions2 . These strategies, policies and procedures must
[1] BCBS Principles for Operational Resilience, March 2021, https://www.bis.org/bcbs/publ/d516.pdf
[2] Tolerance to disruption incidents is the level of disruption from each type of operational risk that an issuer is willing to accept, taking into account a range of severe but plausible scenarios.
THE EXECUTIVE COMMITTEE
be reviewed periodically and updated appropriately.
8. The Management Board ensures that these policies and procedures are effectively implemented, are fully integrated into the overall risk management framework of the entities, including the risk related to the use of third parties, and that they are effectively communicated to the relevant staff.
9. Entities must clearly assign responsibilities for the operational risk and operational resilience assessment and management system.
10. Entities must identify their exposures to operational risk, monitor relevant operational risk data, including data concerning significant losses, and conduct scenario analysis.
11. Entities must identify their critical activities, in accordance with their approach to operational resilience, and map the people, technology, processes, data, facilities, third parties, including intra-group entities, as well as the interconnections and interdependencies between them that are necessary for the performance of critical or important functions both under normal operating conditions and in cases of disruptions.
12. The operational risk management and operational resilience framework must be subject to regular reviews carried out by internal or external auditors, who have the necessary knowledge to carry out such reviews. Also, the operational risk management framework and the operational resilience framework must be structured with adequate and appropriate human and technical resources and be fully integrated into the risk management framework of the entities.
13. A reporting system to the Management Board must be applied, which provides for adequate reports on operational risks and operational resilience from the competent functions within the entities. Entities must have procedures for taking appropriate measures without delay, as the case may be.
14. Entities must identify and assess the operational risk inherent in their activities, processes and systems, so as to ensure that the inherent risks are fully understood.
15. Taking into account Section 2 on the application of the principle of proportionality, entities must identify, analyse and measure a range of scenarios, including low-probability events
THE EXECUTIVE COMMITTEE
occurrence and high severity, some of which could result in serious losses from operational risks. The elements used for scenario analysis include relevant internal and external loss data, information from self-assessments, expert opinions, the internal control framework, indicators for measuring future outcomes, root cause analyses and the process framework, as applicable. The scenario analysis process must be used to develop a wide range of consequences of potential events, including impact assessments for risk management purposes, complementing other tools based on historical data or current risk assessments.
16. Taking into account Section 2, entities may use qualitative risk assessment approaches, while entities issuing significant ARTs must adopt more sophisticated approaches, including, where applicable, the use of internal and external loss data to document scenario analysis.
17. Entities must have policies and procedures for the assessment and approval of new products, processes and systems, including in relation to the new issuance of ARTs and the related processes and systems.
18. The approval process must take into account all risks, including legal risks and ICT risks (Information and Communication Technologies risks), when launching new products and implementing new processes and systems, and must include risks related to people, processes, systems and external events.
19. The approval process must also examine the effects on the performance of critical or important functions and on their interconnections and interdependencies, as well as changes in the operational risk profile of entities, including changes in risks related to existing products or activities, the necessary internal controls, risk management procedures and risk mitigation.
20. Entities must ensure the assessment of the evolution of risks associated with new products, systems and processes over time throughout the life cycle of these products, activities or services.
21. Entities must have a robust internal control system in accordance with Title V of PEE 243/2/07.07.2025 and Section 3 and, with regard to new
THE EXECUTIVE COMMITTEE
products, processes and systems, with the aim of ensuring that they have efficient and effective activities, safeguard their reserve asset, produce reliable information and comply with applicable legislative and regulatory provisions.
22. The internal control framework of an ART issuer, in addition to the requirements of Title V of PEE 243/2/07.07.2025 and Section 3, must ensure:
a) effective and efficient operation, including with regard to the issuance of ARTs,
b) appropriate identification, measurement and mitigation of risks, including operational risk and risks related to ICT, in accordance with Regulation (EU) 2022/2554,
c) reliability of the submitted financial and non-financial reporting, internal and external,
d) sound administrative and accounting procedures, and
e) compliance with laws, regulations, supervisory requirements and internal policies, procedures, rules and decisions of the ART issuer.
23. Entities must establish an ICT risk management framework in accordance with the requirements set out in Regulation (EU) 2022/2554. In this light, entities must have an internal governance and control framework that ensures the effective and prudent management of ICT risks, in order to achieve a high level of digital operational resilience3 .
24. The Management Board of entities that have entered into agreements with third parties for the management of the reserve asset, the investment of the reserve assets, the custody of the reserve assets or, where applicable, the distribution of ARTs to the public or that plan to enter into such agreements must approve, review and regularly update a policy regarding the requirements for the operational reliability of these third parties and ensure their implementation on an individual basis and, where applicable, at group level.
[3] See Regulation (EU) 2022/2554, EE L 333 of 27.12.2022, p. 1–79.
THE EXECUTIVE COMMITTEE
25. The policy must include the main stages of the life cycle of these agreements with third parties and must define the principles, responsibilities and procedures in relation to the use of third-party services. In particular, the policy must cover at least:
a) the responsibilities of the Management Board, including its participation, where applicable, in decision-making,
b) the participation of business sectors, internal control functions and other persons in relation to these agreements,
c) the design and structure of agreements with third parties, including the definition of business requirements regarding the use of third-party services,
d) the identification, assessment and management of risks in accordance with Section 17 of Title V of PEE 243/2/07.07.2025 and this Policy,
e) due diligence controls with regard to potential third parties,
στ) the policies and procedures for the identification, prevention, management and disclosure of conflicts of interest, in accordance with Article 32 of Regulation (EU) 2023/1114,
ζ) business continuity planning and exit strategies to ensure the operational resilience of entities in the event of a failure or disruption at a third party affecting the provision of critical activities. The business continuity and exit plans of entities must assess the possibility of substituting the third party used for critical activities, as well as other viable alternatives that can facilitate operational resilience in the event of a disruption at a third party, such as bringing the activity back in-house,
η) the process for approving new agreements,
θ) the implementation, monitoring and management of those agreements, including the continuous assessment of the performance of third parties, to ensure that the relationship remains within the entities' risk appetite and risk tolerance in the event of disruption of critical activities and essential business areas,
ι) the procedures for notification and response to any changes in an agreement by third parties,
ια) the independent review and independent audit of compliance with legislative and regulatory requirements and policies,
ιβ) the procedures for renewing agreements with third parties,
THE EXECUTIVE COMMITTEE
ιγ) documentation and record-keeping, and
ιδ) exit strategies and termination procedures, including the requirement to have a documented exit plan for each agreement with a third party, if such exit is considered likely taking into account possible service disruptions or the sudden termination of an agreement.
26. Entities must assess the potential impact of agreements with third parties on their operational risk and operational resilience, in accordance with Section 3, and must take into account the results of the assessment when deciding whether a function should be performed by a third party, and must take appropriate measures to avoid unjustified additional operational risks before entering into such agreements.
27. In the context of the risk assessment, entities must take into account the expected benefits and costs of the proposed agreement, including weighing any risks that may be reduced or better managed against any risks that may arise as a result of the proposed agreement, taking into account at least the measures implemented by the entities and the service provider to manage and mitigate those risks.
28. When conducting the risk assessment before creating a dependency on a third party and during the continuous monitoring of the third party's performance, entities must at least:
a) identify and classify the respective functions and the related data and systems based on their degree of sensitivity and importance, as well as the required security measures,
b) carry out a thorough risk-based analysis of the functions and related data and systems considered as the subject of the agreement and address the potential risks, in particular operational risks, including risks from entering into subcontracting arrangements, legal risks, ICT risks, compliance risks and reputational risks, as well as supervisory constraints related to the countries in which the services are –or may be– provided,
c) examine geographical dependencies and the management of the related risks. These risks may relate to the economic, financial, political, legal and regulatory environment of the jurisdiction or jurisdictions where the relevant service will be provided.
29. Before entering into an agreement with a third party and taking into account the risks, including operational risk and counterparty
THE EXECUTIVE COMMITTEE
risk, entities must ensure, within the framework of their selection and assessment process, that the third party is suitable.
30. Entities must ensure that the third party has an appropriate business reputation, appropriate and sufficient capabilities, expertise, ability, resources (e.g. human, IT, financial), organisational structure and, where required, the prescribed supervisory authorisations or registrations required to perform the function reliably and professionally, so that they are able to fulfil their obligations during the term of the contract.
31. Additional factors to be considered when conducting due diligence on a prospective third-party collaborator include, among others, the following:
a) its business model, nature, size, complexity, financial situation, ownership status and the structure of the group to which it belongs,
b) long-term relationships with the third party that has already been assessed and provides services to the entity,
c) the level of substitutability of the service and the service provider, including the ability to exit the agreement with the third party and either transition to another service provider or bring the provision of the critical service back in-house, or the potential impact of such substitution on the entity's critical activities,
d) whether the third party is subject to supervision by competent authorities.
32. Entities must take appropriate actions to ensure that the third party acts in a manner consistent with their values and their code of conduct.
33. Entities must ensure at all times that the third party they use for the distribution of ARTs to the public complies with the procedures that ensure compliance with the obligations concerning the prevention and suppression of money laundering and terrorist financing under Directive (EU) 2015/849 and Law 4557/2018 on the prevention and suppression of money laundering and terrorist financing (transposition of Directive 2015/849/EU) and other provisions (A' 139) and, where applicable, Regulation (EU) 2023/1113 on information accompanying transfers of funds and certain crypto-assets. The third party must ensure the continuous compliance of its internal control systems with the obligations concerning the prevention and suppression of
THE EXECUTIVE COMMITTEE
money laundering and terrorist financing under Directive (EU) 2015/849 and Law 4557/2018 and, where applicable, Regulation (EU) 2023/1113.
34. Without prejudice to the applicable requirements concerning the digital operational resilience of the financial sector (DORA), entities must, in the context of the implementation of the business continuity policy and plans drawn up in accordance with paragraph 9 of Article 34 of Regulation (EU) 2023/1114, draw up a sound business continuity management plan and response and recovery plans, so as to ensure their ability to operate on a continuous basis, to manage incidents that could disrupt the performance of critical activities in accordance with the entities' risk appetite and tolerance for disruptive incidents and to limit losses and disruptions in the provision of services in the event of a severe business disruption. Entities may establish a dedicated independent business continuity function, taking into account the proportionality criteria of Section 2.
35. The business activity of entities relies on various resources of critical importance (e.g. information technology systems, including cloud computing services, communication systems, key personnel and building infrastructure). The purpose of business continuity management is to mitigate the operational, financial and legal impacts, reputational impacts, as well as other significant impacts arising from a disaster or prolonged interruption of these resources and from the consequent disruption of the entities' usual business processes. Other risk management measures may aim to reduce the likelihood of such events occurring or to transfer their financial impact to third parties (e.g. through insurance).
36. In order to draw up a sound business continuity management plan, entities must carefully analyse the risk factors and their exposure to significant disruptions of their business operation and assess (quantitatively and qualitatively) their potential impact using internal and/or external data and scenario analysis. That analysis must test the entity's ability to provide critical activities amid disruptions, as well as cover all business areas and internal units, including the risk management function or risk management processes, while it must also take into account their interdependence. The results of the analysis must contribute to the
THE EXECUTIVE COMMITTEE
determination of the entities' recovery priorities and objectives.
37. Based on the above analysis, entities must have and implement:
a) contingency and business continuity plans, which ensure that entities respond appropriately to emergency conditions and maintain the ability to carry out their critical activities and to preserve important data in the event of an interruption of their usual business processes,
b) recovery plans for critical resources and critical or important functions to recover from disruptions and to provide entities with the ability to return to usual business processes within a reasonable timeframe. Any residual risk from potential operational disruptions must be consistent with the entities' risk appetite,
c) for other activities, or in the event that it is not possible to ensure the continuity of critical essential functions, entities must have procedures for the timely recovery of data and functions and the timely resumption of their activities.
38. Contingency, business continuity and recovery plans must be documented in writing and implemented with particular care. The relevant documentation must be available to the business areas, internal units and the risk management function for the personnel responsible for the risk management processes and must be stored in systems located in separate premises and easily accessible in the event of an emergency. The provision of appropriate training must also be ensured. The plans must be subject to testing and updating at regular intervals. Any challenges or failures identified during the conduct of simulation tests must be documented in writing and analysed, and the plans must be revised accordingly.
39. The strategies, policies and procedures must be communicated to all members of the relevant personnel of the entities. The personnel must understand the policies and procedures concerning their duties and responsibilities and comply with them.
40. The Board of Directors must inform and provide the members of the relevant personnel with up-to-date information regarding the strategies and policies of the entity with clarity and consistency, at least at the level of hierarchy required for the performance of their specific duties. The
THE EXECUTIVE COMMITTEE
said information may be provided through written guidelines, manuals or other means.
41. This shall enter into force upon its publication in the Government Gazette.
42. The Directorate of Credit System Supervision and the Directorate of Inspection of Supervised Companies of the Bank of Greece are authorized, within the scope of their competence, to provide instructions and clarifications for the implementation of this.
43. This shall be published in the Government Gazette and posted on the website of the Bank of Greece.
THE SECRETARY
THE MEMBERS
THE GOVERNOR
Ioannis Stournaras
True copy,
Athens, 17.11.2026
The Secretary
[signed]
I. Pantou
Note from RegAlert. AI assistants can read this document in full, and search 70,000+ more, through the RegAlert MCP connector (https://mcp.regalert.today/mcp). Free with an account. How to connect ChatGPT, Claude or Cursor.
RegAlert holds no document that amends or replaces this one. This is not a check that it is in force: confirm with the regulator.
“Regulation (EU) 2023/1114 of the European Parliament and of the Council of 31 May 2023 ... (L 150/40)”
“Regulation (EU) No 1093/2010 ... (EU L 331/12, 15.12.2010)”
“Part C of Law 5193/2025 “Strengthening of the capital market and other provisions” (A’ 56)”
“Articles 28 and 55A of the Statute of the Bank of Greece (A’ 298/1927)”
“Regulation (EU) 2022/2554 ... (L 333/1)”
More like this from BOG
BOG published 2 documents in the last 30 days. We email you each new one the day it's published.
Source: Bank of Greece — original document · Summary generated with machine assistance and checked by an AI reviewer before publication; the authoritative text is the regulator's original document. How RegAlert works
In RegAlert: added