2006-03-29 | BCP Guideline No. 01/2006Added · Updated
The Central Bank of Sri Lanka issued these guidelines to establish a consistent framework for Business Continuity Planning among licensed commercial banks, primary dealers, and settlement system operators. The document mandates that Boards and senior management assume primary responsibility for BCPs, requiring regular testing, clear recovery time objectives, and the mitigation of interdependency and concentration risks. Financial institutions are required to submit revised BCPs and annual risk management statements to the regulator to ensure operational resilience against disruptions.
CBSL published 2 documents in the last 30 days — get each new one by email the day it lands.
March 29, 2006
BCP Guidelines No: 01/2006
To : Chief Executive Officers of all Licensed Commercial Banks, Primary Dealers, Central Depository Systems (Pvt) Ltd. and LankaClear (Pvt.) Ltd. Guidelines on Business Continuity Planning Introduction
1 )
Includes licensed commercial banks, Primary Dealers and other payment, clearing and settlement service providers supervised/overseen by the Central Bank of Sri Lanka.
Definition of Business Continuity Plan (BCP)
4. ‘Business continuity planning’ refers to: planning and preparation need to be carried out in
advance to identify the impact of potential risks and losses caused by a disruption or a disaster; formulating and implementing viable recovery strategies; and planning to ensure continuity of an institution’s services particularly in the area of core banking/critical businesses, payment, clearing and securities settlement; and administering of comprehensive testing and maintenance. A ‘Business Continuity Plan’ (BCP) refers to a set of processes, procedures, information and measures which are developed, compiled and maintained for critical business functions including core banking and payment and settlement, in readiness for use in an event of an emergency or a disaster which may cause inability to fulfill critical or all business operations. In contrast to BCP, a ‘contingency plan’, refers to measures, which will enable the most critical business functions to be performed in an event of a disruption. Therefore, the concept of BCP is much wider than a contingency plan.
5. Business continuity planning is a culture to be developed at all levels of staff and the required
process needs to be well integrated with the day-to-day operations. The Board and the senior management of each FI should adopt a risk-based framework in BCP. Establishing a comprehensive BCP with a minimum cost without compromising risk management is a challenging task. It would seem sensible for all FIs to have BCPs on the assumption that they may have to face and manage an event of a widespread and prolonged disruption with the complete destruction of buildings and infrastructure in which the main offices of FIs are located, the loss of key staff, complete inaccessibility of the primary site, forcing the FIs to use back-up facilities for an extended period of time. Board of directors (Board) should take responsibility of BCP readiness.
6. FIs may decide to have two-tier plans – one (which would be fully developed with adequate
resources to put into effect immediately) to handle short-term problems; and the other (may be a medium/long term plan) to cope with long-term issues.
7. These guidelines are not intended to prescribe step-by-step guidance as to how FIs should
conduct their BCP process and it could be considered as a minimum. The following of these guidelines will contribute to building a level playing field for all FIs when implementing the BCPs and will help supervisors and overseers to evaluate the resilience of the operations of FIs. Application of the guidelines One of the supervisory/oversight objectives of CBSL is for FIs to have BCPs to ensure high preparedness for continuation of critical operations particularly core banking, payment, clearing and settlement in an event of a disruption. In the course of its on-site examinations, offsite reviews, oversight and meetings on prudential issues with a FI, CBSL will review implementation of the BCP on the practices set out in these guidelines particularly:
staff and executing such a BCP in an event of a contingency. Senior management should endorse business continuity strategies of each system to ensure that plans are consistent with overall business objectives, risk management strategy and financial and other resources. The senior management should also evaluate the adequacy of contingency planning for each system and its periodic testing by its own staff/service providers whenever critical operations are outsourced. Resilience and recovery measures should adequately cover the level of business activity, risk tolerance and its role in preserving the systemic stability of the financial system. Such measures should be clearly stated in the BCP and regularly reviewed. Senior management should be accountable to the Board for achieving the stated objectives of each system in the BCP and submit a report to the Board at least annually indicating clearly:
Back Office, building/premises, human resources and communication) who would direct the recovery operations.
FI must develop, implement and maintain a BCP document, which provides guidance for
crisis management procedure and information, which enable the senior management of FI to respond to disruption and recover critical businesses in a contingency event to avoid contagion effect on business of the FI as a whole.
The dimension of a disruption is another important element to be considered in identifying
scenarios. The best practice is for senior management to identify all plausible crisis scenarios including disasters covering a wide area, transportation, telecommunication, key personnel, payment system and other key infrastructure and develop crisis management process and procedures. Scenarios should be documented and revised when regular business impact analysis requires them to be changed. The crisis management process at a minimum should include:
The process for ensuring early detection of an emergency/contingency and prompt
notification to the DMT about the incident;
The process for the DMT to assess the overall impact on the respective institution and to
make quick decision on the appropriate action;
Clear criteria for activation of the BCP and/or alternate sites;
The process for obtaining information on the status of the recovery process;
A process for timely internal and external communication; and
A process for overseeing the recovery and restoration efforts of the affected
services/facilities.
The best practice is for each business/support function to establish a business recovery team
(which may have sub teams) to carry out the business resumption process. FI should assign recovery personnel (as well as alternate personnel) with required knowledge/skills to each such team.
Business resumption process generally has three phases:
The mobilization phase – This phase involves notification to business recovery teams
(using call-out tree, the predefined sequence of points of contact of staff for dissemination of information) and vendors to obtain required services; and follow predetermined sequence in the BCP (or revising the sequence if it is necessary);
The alternate processing phase – This phase involves the resumption of the
business/service at DRS/or in a different way than the stipulated process. This may need record reconstruction and verification, establishment of new controls, alternative manual processes and alternative ways of dealing with customers/counterparties.
The full recovery phase - This phase involves a process for moving back to the primary
site after a disaster/contingency event.
The BCP should: identify and plan for activities which would be required under each phase of
business resumption process; establish clear responsibilities; and develop and include recovery task’s checklist.
FI should pay special emphasis to ensure resilience of critical technology
equipments/facilities to reduce the probability of having to activate the BCP in an inevitable disruption to business. The technology requirement for recovery of each business/support function should be specified in the recovery strategy for each function and FI should assign appropriate personnel/with alternate personnel for recovery of technical failures.
FI may use an appropriate business continuity model to handle prolonged disruptions, based
on the risk assessment of their business environment and the characteristics of their own operations.
Each BCP should clearly identify the recovery point objectives for data losses for each of the
critical system and the strategy to handle such data losses and information deemed vital for recovery of critical business/support functions in the event of a contingency/disaster. Some of the protection measures:
Back-up vital records must be readily accessible for emergency retrieval;
Access to back up vital records should be adequately controlled to ensure the
reliability of them for the use of business resumption.
Clear procedure indicating how and in what priority the vital records to be
retrieved/created in the event that they are lost/damaged/destroyed.
Institution should formulate a formal strategy for internal as well as external
communication with key external parties (regulators, investors, customers, counterparties, service providers, the media and other stakeholders) to ensure dissemination of up-to-date and consistent information in a contingency situation. Guideline 3: Test each aspect of the BCP regularly, completely and meaningfully
systems) in Sri Lanka, and to develop recovery strategies as well as RTO to mitigate risks. A business continuity arrangement of a FI should not introduce any risk to a systemically important or systemwide important payment, clearing and settlement system, its operator or participants and each FI should have an independent BCP for widespread and prolonged disruption to its infrastructure and critical services, without relying on another participant of such systems. If any critical functions are dependent on outsourced arrangements, adequate provisions should be in place to ensure operation of services by third parties. Guideline 6: Plan for wide-area and prolonged disruptions
14. FIs should provide measures for scenarios, which may result significant losses or
inaccessibility of critical infrastructure including SWIFT and telecommunication where there is a widespread or prolonged disruption. Guideline 7: Practice separation policy to minimize concentration risk
15. FIs should practice separation policy to mitigate concentration risk. Disruptions may result in
a non-availability of critical staff, information and required telecommunication links and payment infrastructure such as SWIFT. FIs should balance and properly mitigate concentration risk, while not sacrificing the efficiency gains from centralization of business processes and staff. Accordingly, FIs should take measures to separate critical business operations by:
Note from RegAlert. AI assistants can read this document in full, and search 70,000+ more, through the RegAlert MCP connector (https://mcp.regalert.today/mcp). Free with an account. How to connect ChatGPT, Claude or Cursor.
Source: Central Bank of Sri Lanka — original document · Summary generated with machine assistance and reviewed before publication; the authoritative text is the regulator's original document. How RegAlert works
More like this from CBSL
CBSL published 2 documents in the last 30 days. We email you each new one the day it's published.