Rule · SBP · 5 Oct 2026 · DI&SD Circular No. 02 of 2026
Financial Institutions must create public awareness about PECS, operate the system by April 30, 2027, and nominate focal persons reporting progress to SBP. Presenting institutions must capture compliant electronic images, mark instruments as truncated, and credit customers upon finality. Paying institutions must retrieve images, verify genuineness, and decide payment by the Return Session cut-off. Participants must maintain settlement balances, reconcile items daily, and retain records per the Payment Systems and Electronic Fund Transfers Act, 2007. Clearinghouse must conduct annual VAPT and ensure two-hour recovery time.
DI&SD Circular No. 02 — October 05, 2026
All Clearinghouse (NIFT) Members
Dear Madam/Sir,
Launch of the Pakistan Express Clearing System (PECS)
In order to strengthen digital payments ecosystem of Pakistan and enhance the efficiency of the existing cheque clearing and settlements mechanism, it has been decided to introduce Pakistan Express Clearing System (PECS). The new system will be based on the concept of cheque truncation as defined in Section 2(zl) of the Payment Systems and Electronic Fund Transfers (PS&EFT) Act 2007, under which cheques will be cleared on the basis of images captured, instead of physical instruments. Images will be captured by the Presenting/Collecting bank and will be transmitted to Clearing House (NIFT) for onward transmission to Paying/Drawing bank for processing the cheque/instrument.
Enclosed:
Yours sincerely,
Muhammad Imaduddin
Director
Implementation Plan for Pakistan Express Clearing System (PECS) a) With Limited Scope & Limited Participants (October 15, 2026, to November 15, 2026). PECS shall initially be implemented at selected Clearinghouse Participating Institutions designated by SBP in consultation with the Clearinghouse. Subsequently, the Clearinghouse and the Participating Institutions shall jointly review the outcomes of the pilot phase and address any related issues. Further, the Clearinghouse shall submit a consolidated readiness report to SBP. b) Limited Scope & All Participants (November 16, 2026, to December 31, 2026). PECS shall subsequently be extended to the remaining Clearinghouse Participating Institutions, incorporating the learnings from the Initial Pilot phase. All Participating Institutions shall operate PECS in accordance with the prescribed Rules and shall progressively extend truncation capability across their branch networks. c) Complete Roll out (by April 30, 2027). All Clearinghouse Participating Institutions shall develop the required infrastructure as per the requirements of clearinghouse and shall achieve nationwide implementation of the PECS by April 30, 2027. d) Each Participating Institution shall nominate a focal person for PECS implementation and shall report implementation progress to SBP. Participating Institutions shall ensure compliance with the prescribed clearing timelines, customer service standards and settlement obligations throughout the implementation process without disruption. e) During the pilot phase, from October 15, 2026 to December 31, 2026, an additional PECS clearing cycle shall be operated daily, which the Clearinghouse shall submit to SBP by 3:00 pm. *
Digital Innovation & Settlements Department
Pakistan Express Clearing System (PECS) Rules
Table of Contents
1. Authority.............................................................................................................................................................. 1
2. Definitions........................................................................................................................................................... 1
3. Scope and Application......................................................................................................................................... 2
4. Exclusions............................................................................................................................................................ 2
5. Roles and Responsibilities................................................................................................................................... 2
5.1 Presenting/Collecting Institution................................................................................................................... 2
5.2 Drawee/Paying Institution............................................................................................................................. 3
5.3 The Clearinghouse......................................................................................................................................... 4
6. Clearing Cycles..................................................................................................................................................... 4
7. Deferrals, Returns and Return Integrity .............................................................................................................. 4
7.1 Defer for Physical (DFP)................................................................................................................................. 4
7.1.1 Permitted grounds for DFP......................................................................................................................... 4
7.2 No-Pay effect................................................................................................................................................. 4
7.3 DFP and Returns integrity.............................................................................................................................. 5
8. Settlement........................................................................................................................................................... 5
8.1 Submission & Settlement.............................................................................................................................. 5
8.2 Failure to settle.............................................................................................................................................. 5
9. Data Security and Retention................................................................................................................................ 5
9.1 Security of data transmission and systems................................................................................................... 5
9.2 Retention....................................................................................................................................................... 5
10. Compensation and Recovery............................................................................................................................. 5
10.1 Delayed credit and recovery ....................................................................................................................... 5
10.2 Direct customer loss.................................................................................................................................... 5
10.3 Forged or Counterfeit Instruments............................................................................................................. 5
11. Business Continuity and Bureau Service ........................................................................................................... 6
11.1 Continuity .................................................................................................................................................... 6
11.2 Participant contingency plans..................................................................................................................... 6
11.3 Clearinghouse continuity............................................................................................................................. 6
11.4 Unavailability of the Clearinghouse ............................................................................................................ 6
12. Notification, Reporting and Oversight............................................................................................................... 6
12.1 Notification and Response .......................................................................................................................... 6
12.2 Reporting..................................................................................................................................................... 6
12.3 Internal Controls and Audit......................................................................................................................... 7
13. Customer Awareness and Disclosure ................................................................................................................ 7
14. Dispute Resolution ............................................................................................................................................ 7
Annexure A — Acronyms ........................................................................................................................................ 7
1. Authority
These Rules are issued by the State Bank of Pakistan in exercise of the powers vested under the Payment Systems and Electronic Fund Transfers (PS&EFT) Act, 2007.
2. Definitions
2.1 Assigned Branchmeans a branch designated by a financial institution to receive, process, and clear cheques
on behalf of another branch of the same financial institution.
2.2 Bank means a banking company as defined in the Banking Companies Ordinance, 1962.
2.3 Bureau Service means the image-capture service of the Clearinghouse used by a presenting institution as
a backup and business-continuity arrangement.
2.4 Cheque has the same meaning as defined in Negotiable Instruments Act, 1881.
2.5 Clearing Calendar means the schedule of business days, sessions and cut-off times maintained under the
authority of SBP.
2.6 Compliant Scanner means a scanner conforming to the scanner specifications agreed between the
Clearinghouse and member financial institutions and producing exact electronic images to the agreed Image Quality Assurance standards.
2.7 CPU (Central Processing Unit) means a centralized processing location that receives, validates, routes and
processes instruments for one or more home branches in accordance with configured routing rules.
2.8 Defer for Physical (DFP) means the status by which a paying institution, unable to reach a final decision on
the Electronic Image, requests delivery of the original instrument before recording a final fate.
2.9 Designated Branch means a branch of the presenting institution equipped with a Compliant Scanner to
truncate instruments at the point of deposit.
2.10 Drawee/Paying Institution means the institution on which the instrument is drawn and which records the
Pay or No-Pay decision on the Electronic Image.
2.11 Electronic Image means the exact image of a paper-based payment instrument in electronic form and is
generated, written and signed using a secure system authorized by SBP.
2.12 Fate means the Pay, No-Pay or Defer for Physical outcome recorded by the paying institution on the
Clearinghouse system.
2.13 Finality has the same meaning as defined in PRISM+ operating Rules, 2026.
2.14 Force Majeure means any delays or failures in the performance of a Clearinghouse and/or
Presenting/Paying Institutions and to the extent it is caused by the occurrences or circumstances beyond reasonable control of Clearinghouse and/or Presenting/Paying Institutions, including but not limited to, acts of God, fire, strikes or other labor disturbances, riots, civil commotion, war or any other causes similar to those specified herein.
2.15 Genuineness Warranty means the warranty given by the presenting institution as to the genuineness and
apparent good order of the physical instrument on physical inspection.
2.16 Grievance Redressal Process means the complaint-handling mechanism of a participating institution
through which an unresolved PECS complaint is escalated.
2.17 Home Branch means the branch associated with the account on which the cheque is drawn. It is the branch
which serves as the destination for cheque routing and processing, unless overridden by centralized processing or other bank-defined routing rules.
2.18 Image Quality Assurance (IQA) means the agreed standards, between the Clearinghouse and participating
institutions, that a captured image must satisfy before presentment.
2.19 Multilateral Net Settlement Batch (MNSB) means the net position of all participants submitted by the
Clearinghouse to SBP for settlement.
2.20 Participating Institution/Financial Institution means a member institution of the Clearinghouse that
participates in the clearing process under the Truncation System.
2.21 Payment Order has the same meaning as defined in guidelines issued by SBP vide PSD circular No. 4 of
2015.
2.22 Presenting / Collecting Institution means the institution at which the beneficiary deposits the instrument
and which captures and transmits the Electronic Image and clearing data to the Clearinghouse.
2.23 Presentment Session means the clearing window within which presenting institutions lodge Electronic
Images and clearing data.
2.24 PRISM+ / RTGS means the real-time gross settlement system of SBP.
2.25 Return Session means the clearing window within which the paying institution must record Pay, No-Pay or
Defer for Physical.
2.26 Clearinghouse means the Clearinghouse authorized by SBP for clearing operations.
2.27 Secure System means infrastructure compliant with the Payment Systems and Electronic Fund Transfers
Act, 2007 and other applicable laws, incorporating end-to-end encryption, multi-factor authentication, tamper-evident audit logs, PKI digital signatures and any other applicable requirement.
2.28 Truncated Cheque has the same meaning as defined in PS&EFT Act, 2007
3. Scope and Application
These Rules shall apply to:
– Presence of the required endorsement (signature) – Whether signature appears to be printed or stamped – Absence of material alteration (doubtful/ cutting, overwriting or alteration without signature) – Whether the instrument is torn or mutilated – Payee particulars, including name (Self, Cash, without name) and correctness of the crossing
5.3 The Clearinghouse
The Clearinghouse shall be responsible for:
7.2 No-Pay effect
A No-Pay decision shall carry a standardized return reason code from the catalogue of codes as decided between the Clearinghouse and participating members. The practice of delaying clearance of instruments by marking them as returned or invoking Defer for Physical, without proper cause, is prohibited and shall be treated as a serious compliance failure.
7.3 DFP and Returns integrity
Each participating institution shall maintain a branch-wise register of all instruments returned and all items marked DFP, recording the reason code, the timestamp, the relevant bank-official and the eventual resolution.
8. Settlement
8.1 Submission & Settlement
The Clearinghouse shall compute the net position of every participant from the recorded fates and shall submit one MNSB per cycle to PRISM+ as a Special Participant. Settlement of the MNSB constitutes asfinal and irrevocable settlement in accordance with the Payment Systems and Electronic Fund Transfers Act, 2007. A participant in a netdebit position shall hold sufficient balance in its settlement account to meet the settlement obligation.
8.2 Failure to settle
Where a participant in a net-debit position is unable to settle within the prescribed window, the failure-to-settle provisions of the PRISM+ Operating Rules shall apply, which may include recalculation, unwinding of the batch or re-submission, and any late-settlement penalty or charges. Participants shall remain liable for their clearing obligations notwithstanding any operational failure.
9. Data Security and Retention
9.1 Security of data transmission and systems
Instruments’ images shall be captured, transmitted, processed, stored and retained in a secure system, to preserve the confidentiality, integrity, authenticity and availability of Electronic Images and clearing data, and to protect them against loss, unauthorized access and undetected alteration, from the time of capture through archival.
9.2 Retention
Electronic cheque images and associated clearing records form part of the electronic transaction record and shall be retained in accordance with Section 7 of the Payment Systems and Electronic Fund Transfers Act, 2007. Retention of original physical instruments shall continue to be governed by existing policies, practices and applicable legal and regulatory requirements.
10. Compensation and Recovery
10.1 Delayed credit and recovery
The Presenting Institution shall immediately credit the payee’s account once fate of the instrument is updated on the PECS portal. Where the payee’s account is not credited in a timely manner, the compensation policy of Electronic Fund Transfers (EFT) Regulations issued by SBP vide PSD Circular No. 3 of 2018 shall apply.
10.2 Direct customer loss
Where a customer suffers a direct loss and the customer was neither complicit in fraud nor grossly negligent, the responsible institution shall compensate the customer. The claim shall be acknowledged within two (2) business days of receipt and resolved within ten (10) calendar days of acknowledgment.
10.3 Forged or Counterfeit Instruments
In case the drawer denies having authorized the payment and claims the cheque is fraudulent or materially altered, the paying institution shall request retrieval of the original Instrument and shall pursue recovery in accordance with law. Where the paying institution has reasonable grounds to conclude that a paid instrument was forged or counterfeit, it shall refer the matter to the presenting institution under the Genuineness Warranty together with the supporting evidence. The presenting institution shall take up the matter with its customer and shall provide its findings to the Paying bank as to whether the warranty has been breached. Where breach of the Genuineness Warranty is established, the presenting institution shall recover the amount from the beneficiary and reimburse the paying institution. The decision on such a referral shall be finalized within ten (10) days of the referral by the paying institution.
11. Business Continuity and Bureau Service
11.1 Continuity
Continuity of clearing shall be supported through appropriate contingency arrangements in the event of failure of a participant’s scanning capability, connectivity or premises, or of the Clearinghouse’s own systems. Where a branch has no operational scanning capability or experiences an outage, the presenting institution may route physical instruments to the nearest Designated Branch or use the Bureau Service of the Clearinghouse. The Clearinghouse shall scan and capture the instruments, in accordance with IQA standards, into the clearing system, while ensuring the overall integrity of the instrument.
11.2 Participant contingency plans
Each participant shall maintain a documented contingency plan for scanning, connectivity and portal access, including alternate capture sites and recourse to the Clearinghouse, and shall test it at least bi-annually.
11.3 Clearinghouse continuity
The Clearinghouse shall operate business-continuity arrangements for the system and the delivery function. The Clearinghouse service shall maintain a recovery time objective of not more than two (2) hours and a recovery point objective of not more than fifteen (15) minutes for PECS-critical functions. The backup service shall operate on infrastructure independent from the location and technology stack from the primary systems of the Clearinghouse, and shall be tested at least bi-annually, with the results reported to SBP.
11.4 Unavailability of the Clearinghouse
Where the services of the Clearinghouse are not available, the Clearinghouse shall establish a mechanism for communication of the clearing obligations to the participating institutions and submission of MNSB to SBP via alternative modes. Participating institutions shall also devise internal mechanisms to settle their clearing obligations through their respective branches, treasuries or head offices using PRISM+.
12. Notification, Reporting and Oversight
12.1 Notification and Response
The Clearinghouse shall operate an automated notification system to alert paying and presenting institutions to clearing events, including presentment, availability for decisioning, fate updates, DFP status and settlement. Participating Institutions shall act promptly on notifications; debit or credit customer accounts accordingly upon clearance and notify customers through communication channels like SMS, email, in-app notifications or similar channels.
12.2 Reporting
The Clearinghouse shall maintain the master clearing record, timestamps and audit trails and shall make them available to the participantsfor reconciliation and dispute resolution. Each participant shall reconcile its presented, settled, returned and deferred items against the master clearing record of the Clearinghouse and against its settlement account on daily basis. SBP may inspect, call for records/MIS, and take supervisory or enforcement action in accordance with applicable laws and regulations in respect of non-compliance.
12.3 Internal Controls and Audit
Each participant shall establish internal controls to ensure compliance with these Rules and shall subject the truncation process to periodic internal audit to ensure compliance with the overall PECS integrity.
13. Customer Awareness and Disclosure
Participating institutions shall create public awareness, through print, electronic and social media, regarding proper presentment of cheques and the safeguards that reduce fraud and forgery risk under truncation, including the significance of correct crossing and legibility. Participants shall prominently display the customer presentment cutoff time for each clearing cycle at all branches and on their websites. They shall further inform customers of their rights in respect of instruments cleared under PECS, including the right to a certified copy of a paid instrument, the applicable timelines for disputing a wrongly charged or wrongly cleared instrument and the complaint escalation route available to them.
14. Dispute Resolution
A customer with an unresolved complaint concerning an instrument cleared under PECS, including wrongful debit, non-credit, or a dispute as to a compensation claim, may escalate the matter through the Grievance Redressal Process of the relevant participating institution.
Annexure A — Acronyms
Acronym Expansion
BCP Business Continuity Plan
CBC Call Back Confirmation
CH Clearinghouse
CPU Central Processing Unit
DFP Defer for Physical
DI&SD Digital Innovation & Settlements Department EFT Electronic Fund Transfer FI Financial Institution IBCS Image Based Clearing System IQA Image Quality Assurance MFA Multi-Factor Authentication MFB Microfinance Bank MIS Management Information System MNSB Multilateral Net Settlement Batch PECS Pakistan Express Clearing System PKI Public Key Infrastructure PKR Pak Rupee PRISM+ Pakistan Real-time Interbank Settlement Mechanism Plus PS&EFT Act Payment Systems and Electronic Fund Transfers Act, 2007 PSD Payment Systems Department RPO Recovery Point Objective RTGS Real Time Gross Settlement RTO Recovery Time Objective SBP State Bank of Pakistan VAPT Vulnerability Assessment and Penetration Testing
PECS Procedures
STATE BANK OF PAKISTAN
Digital Innovation & Settlements Department
Procedures and Operational Instructions for
Pakistan Express Clearing System (PECS)
PECS Procedures
PECS Procedures branch is not available, the instrument shall be routed for Bureau capture (Section 4.2 and 4.3 below).
3.3 The Image Quality Assurance (IQA) engine configured with the Presenting Institution shall perform
the IQA against each scanned instrument. If the IQA is successful, the image shall be included in Image Cash Letter (ICL) files (batches) and transferred through the secured connectivity to the Clearinghouse (Section-4.4 to 4.6 below).
3.4 The presenting branch shall mark the instrument as “Presented for Truncation” (Section 4.7
below).
3.5 Upon receipt of the ICL batches from Presenting Institution, Clearinghouse shall perform the
required validation and send the files to the Paying Institution (Section 4.8 to 4.10 below).
3.6 The Paying bank shall retrieve the images from Clearinghouse system, and determine the fate of
Instrument as Pay, No-Pay, or Defer for Physical. Defer for Physical option shall be invoked if the Paying Institution is not satisfied with the veracity of the Instrument or its Electronic image (Section 4.11 to 4.21 below).
3.7 The Clearinghouse shall inform the Presenting Bank about the decision and prepare the
settlement batches for submission to PRISM+.
4. Process Details
Instrument Deposit and preliminary examination
4.1 Upon receiving the Instrument from a customer, the presenting branch shall physically examine
the instrument for apparent tenor, validity, authenticity and genuineness before capture. An instrument that fails preliminary examination shall not be truncated and shall be returned to the depositor at the counter with proper disclosure. The reason for non-acceptance shall be recorded in the branch record. Image capture and quality assurance
4.2 An instrument that passes preliminary examination shall be scanned at the branch to produce a
compliant Electronic Image along with the required clearing data set. Capture of instrument shall be performed on a Compliant Scanner, configured in accordance with the image specification agreed between the Clearinghouse and participating institutions.
4.3 Where a presenting branch has limited operational scanning capability, instruments deposited at
that branch shall be routed to the nearest designated Branch for capture or presented through the nearest Bureau Service offered by the Clearinghouse.
4.4 The IQA engine of Clearinghouse system shall automatically screen each captured image against
the defected conditions notified under the IQA standard. An image that fails IQA shall be recaptured. However, if an instrument repeatedly fails IQA, the branch shall re-examine the instrument physically, adjust capture settings or scanner condition as required, and, where a compliant image still cannot be produced, the branch shall make alternative arrangements like
PECS Procedures capturing through nearby designated branch, Bureau Service, or presenting the instrument through Normal (Non-Truncated) clearing.
4.5 The Presenting Institution shall prepare ICL files containing the scanned images and comply with
all necessary instructions in this regard. Before transmitting the image to the Clearinghouse, the presenting branch shall validate the captured clearing data against the instrument, with particular attention to the amount, date, the drawee routing and branch code, the instrument number and the account number.
4.6 Presentment shall be considered complete only when the Clearinghouse acknowledges receipt of
a valid, IQA-compliant item; an item transmitted but not acknowledged is not “Presented for Truncation”. The presenting institution shall monitor for acknowledgment and resolve unacknowledged items before the applicable cut-off. Franking or Marking the Instrument
4.7 The process of marking a physical Instrument is referred to as Franking. The presenting institution
shall indelibly Mark or Frank the physical instrument as “Presented for Truncation” after receiving confirmation from the Clearinghouse that the instrument is IQA-compliant. Franking shall be carried out in a manner that enables the system to recognize that the instrument has been previously presented and that its image has been submitted in Clearinghouse system. Franking shall not obscure the drawer's signature, the amount fields, the date, the payee particulars, the crossing or the code line.
4.8 The Clearinghouse shall validate each item for structural completeness and data integrity, run
duplicate detection against prior and concurrent presentments, record the item in the master clearing record with a timestamp, and make the Electronic Image and clearing data available to the relevant paying institution.
4.9 Items rejected during Validation shall be reported back to the presenting institution with the
rejection reason. The presenting institution shall correct the identified issue and re-transmit. A validation rejection shall not constitute a return and shall not be communicated to the customer as a return.
4.10 Items flagged as suspected duplicates shall be quarantined by the Clearinghouse, and shall not
form part of the clearing cycle, and shall be referred to the presenting institution for resolution. The presenting institution shall examine the franking and lodgment history of the underlying physical instrument, confirm whether an authorized lodgment exists, and respond to the Clearinghouse accordingly. A quarantined item confirmed as a genuine single presentment may be released for presentment and an item confirmed as a duplicate shall be withdrawn. The presenting institution shall monitor the fate of each presented item on the system until a final Fate is recorded.
PECS Procedures
Decisioning and Recording of Fate
4.11 The paying institution shall retrieve the Electronic Image and clearing data from the Clearinghouse
system, and record the fate as Pay, No-Pay or Defer for Physical.
4.12 In the case of a Pay decision, the Clearinghouse shall inform the Presenting Bank of the decision
and prepare the settlement batches for submission to PRISM+. The Paying Bank shall send an online notification to their customers about presentment of their instruments along with the Paid status, and shall debit their accounts. Accordingly, the Presenting Bank shall immediately credit the customer account and make the funds available.
4.13 In case of No-Pay decision, Clearinghouse shall inform the Presenting Bank about the decision and
the instrument shall be excluded from the settlement batch. The Paying Bank shall send an online notification to their customers about presentment of their instruments along with the No-Pay status. Accordingly, the Presenting Bank shall also inform their customers about the No-Pay decision. Defer for Physical (DFP)
4.14 DFP shall be invoked where a final decision can not be made properly on the Electronic Image. It
is a controlled exception and shall not be used to obtain additional time, manage internal targets, or defer decisions that can reasonably be made on the basis of the Electronic image.
4.15 The paying institution shall record DFP against the item on the Clearinghouse portal by the
applicable Return Session cut-off, with a valid reason code from the Return & DFP code catalogue agreed between the Clearinghouse and the member participants.
4.16 On receipt of a DFP marking, the Clearinghouse shall identify the specific original instrument held
by the presenting institution and arrange its expedited delivery to the paying institution, in accordance with the timelines of the clearing cycle to which the deferred item is routed. Deferred original instruments shall be delivered separately from the routine periodic consignment and shall not be held back for that cycle.
4.17 The presenting institution shall release the specific deferred original instrument on the
Clearinghouse's request and shall record the hand-off.
4.18 In intercity clearing, the Clearinghouse shall deliver deferred original instruments to the paying
institution's Central Processing Unit (CPU) or an Assigned branch located in the city of presentment. This shall ensure that the fate of intercity instruments can be finalized within the prescribed clearing cycles. Where the paying institution specifically requires delivery to the Home Branch instead, delivery shall be made to that branch no later than two working days.
4.19 Upon receipt of the original instrument, the CPU or assigned branch, or the Home Branch, as
applicable,shall record the final fate within the timeline prescribed for the relevant clearing cycle, so that the item is either cleared or returned. No item shall be left without a final Fate.
PECS Procedures
4.20 Where fraud, forgery or material alteration is suspected at the time of decisioning, the paying
institution shall invoke DFP or request retrieval of the original instrument.
4.21 The Clearinghouse shall report DFP volumes, ageing and resolution times to SBP as part of the
periodic clearing MIS, and shall bring persistent deferral patterns to the attention of SBP.
5. Operational Readiness
5.1 The presenting institution shall ensure that the branch has:
PECS Procedures
5.7 Where an instrument is at or above a value threshold prescribed by SBP, or a threshold set by the
institution under its own risk management framework, the paying institution shall apply enhanced verification before recording the fate as paid. Enhanced verification may include Call Back Confirmation (CBC), Multi-factor Authentication (MFA), or retrieval of the details submitted by the drawer prior to presentment in Section 5.5 above.
5.8 Where the drawer of a paid instrument requests a certified copy, the paying institution shall issue
a certified copy of the Electronic Image together with confirmation of the Pay decision, the date of decision and the clearing reference, through its established customer-service channel, and shall log the request and its fulfilment. Banks shall clearly communicate the channel available for such requests.
6. Returns and Return Integrity
6.1 A No-Pay Fate shall carry a standardized return reason code from the catalogue agreed between
the Clearinghouse and participating members. The code selected shall accurately reflect the actual ground of return. A general or “any other reason” code shall be used only where no specific code applies and shall be accompanied by an explanation.
6.2 No-Pay items shall be excluded from the Multilateral Net Settlement Batch (MNSB) and shall not
be settled. The presenting institution shall inform the customer of the reason promptly on receipt of the return, using the reason as recorded and without substituting a different or softened explanation. Return and deferral integrity
6.3 Each participating institution shall maintain a branch-wise record of all instruments returned and
all items marked DFP, recording the reason code, the timestamp, the deciding staff member and the eventual resolution.
6.4 Each institution shall operate a monitoring process, at a frequency appropriate to its volumes and
at minimum monthly, to identify branches or staff with anomalous return or deferral patterns. Indicators to be monitored include unusually high return rates relative to peer branches, repeated use of soft or general reason codes, returns concentrated near cut-off, and DFP events that resolve to Pay without a substantive defect having been found.
6.5 Where the monitoring process identifies returns or deferrals that were marked without proper
cause, the institution shall investigate the matter, take punitive action against the staff or branch concerned, and record such action in its compliance register.
7. Clearing Cycles, Cut-offs and Cut-off Extension
7.1 Clearing shall operate through Truncation Cycles and Non-Truncation Cycles in accordance with
the session schedule communicated by SBP.
PECS Procedures
7.2 In a Truncation Cycle: presenting institutions shall lodge Electronic Images and clearing data; the
Clearinghouse shall validate and make items available to paying institutions; Paying institutions shall record fate before the MNSB submission time prescribed for that cycle; the Clearinghouse shall submit the MNSB to PRISM+ for settlement and presenting institutions shall release customer credit without delay upon Settlement Finality.
7.3 Items recorded as DFP shall be routed to the Non-Truncation Cycle designated for that purpose
in the session schedule.
7.4 In a Non-Truncation Cycle: non-standard instruments collected up to the customer collection cutoff for that cycle, together with items routed as DFP, shall be processed. Paying institutions shall
complete physical inspection and finalize fate in respect of both categories before the MNSB submission time for that cycle. The Clearinghouse shall submit the MNSB; and presenting institutions shall release customer credit without delay upon settlement Finality.
7.5 Where the Clearinghouse is unable to process a cycle within the prescribed cut-off owing to a
system issue or an event beyond its reasonable control, it shall request SBP in writing to extend the cut-off for the affected cycle, stating the cause, the extension sought and the expected impact. The Clearinghouse shall record each extension and its cause in the periodic clearing MIS.
8. Custody, Retention and Retrieval of Physical Instruments
Custody of the physical instrument shall pass through three phases: interim custody at the presenting institution; delivery by the Clearinghouse; and archival custody at the paying institution. Chain of custody and an auditable record shall be maintained at every hand-off by the Clearinghouse. Interim custody
8.1 From capture until collection by the Clearinghouse, the presenting institution shall retain each
truncated instrument securely, in a manner that protects it against loss, damage, unauthorized access and unauthorized re-lodgment. Delivery by the Clearinghouse
8.2 The Clearinghouse shall collect retained physical instruments from presenting institutions and
deliver them to the respective paying institutions on a T+1 basis or as prescribed by SBP from time to time. Each consignment shall be accompanied by a manifest reconciling the physical instruments to the settled clearing record. Both the delivering and the receiving party shall acknowledge the hand-off, and discrepancies between the manifest and the consignment shall be recorded at the point of hand-off and referred to the Clearinghouse for resolution. Archival custody and retention
8.3 On receipt of a consignment, the paying institution shall verify it against the manifest, take the
instruments into archival custody and retain them securely for the applicable retention period.
PECS Procedures
The paying institution shall maintain an index enabling any retained instrument to be located and produced.
8.4 Retention of Electronic Images and associated clearing records shall be governed by the applicable
statutory retention requirement; retention of original physical instruments shall continue to be governed by existing policies, practices and applicable legal and regulatory requirements. Retrieval on demand
8.5 The custodian of a physical instrument shall produce the original instrument upon the valid
request for the purposes of dispute resolution, investigation of suspected fraud or forgery, or legal proceedings.
8.6 Instrument retrieval requests shall be logged including recording the requesting party, grounds
for the request, date of request, date of delivery of the instrument, and manner of production.
9. Management Information and Reporting
9.1 Participants and the Clearinghouse shall submit clearing MIS to SBP in the form and at the
frequency prescribed by SBP. The MIS shall cover, as applicable:
PECS Procedures
10.3 Institutions shall maintain documented user-administration procedures covering provisioning,
modification and prompt revocation of access on transfer or exit, segregation of duties between capture, decisioning and administration, and periodic review of user entitlements at least halfyearly.
10.4 Access to the PECS portal and all submission of data and images to the Clearinghouse shall use
certificate-based authentication under the Public Key Infrastructure established for PECS, in addition to role-based access controls. Institutions shall manage certificate issuance, renewal, revocation and safe custody of private keys, and shall notify the Clearinghouse immediately of any suspected compromise of a key.
10.5 Electronic Images and their associated data shall be secured in a manner that ensures attribution
to the presenting institution and tamper-evident from capture through archival. The Clearinghouse shall provide the necessary setup and issue implementation guidance to participating institutions in this regard.
10.6 Customer and account data handled in clearing process shall be used only for clearing, settlement,
reconciliation, and dispute resolution.
11. Customer Awareness and Staff Training
11.1 Participating Institutions shall conduct public awareness activity through print, electronic and
social media regarding the proper presentment of instruments and the safeguards that reduce the risk of fraud and forgery under truncation, including the significance of correct crossing, legibility, and the availability of the in-app facility described in Section 5.5.
11.2 Participating Institutions shall prominently display the customer presentment cut-off time for
each clearing cycle at all branches and on their websites and shall keep customers informed of any changes to the Clearing Calendar.
11.3 Participants Institutions shall inform customers of their rights in respect of instruments cleared
under PECS, including the right to a certified copy of a paid instrument, the applicable timelines for disputing a wrongly charged or wrongly cleared instrument, and the complaint escalation route.
11.4 Branch and operations staff shall be trained before a branch is designated for truncation, and on
a continuing basis thereafter. Training shall cover the capture process and scanner operation, preliminary examination, IQA and re-capture, franking, data validation, the correct use of return reason codes, the proper use and limits of Defer for Physical, enhanced verification for high-value instruments, and custody obligations.
PECS Procedures
Annexure-A : Process Flow
Yes
No
Yes
No
Paying
Institution
-
Presenting
Branch /
Institution
Clearinghouse
Customer presents instrument i
Verify instrument
2a.
Acceptable?
Return to customer with reason
Scan instrument a. Scan at presenting branch (if capable) b. Else route to designated branch
c. Else bureau capture
IQA
(Clearinghouse engine, bank -side)
4a.
Passed?
Return for rescan
Create & transmit ICL batch; mark “Presented for Truncation” Validate ICL batch 6a.
Valid?
Return to presenting institution
Forward validated ICL batch to paying institution Retrieve image & decide fate Pay (Accept for payment) No-Pay (Return / reject) Defer (Request physicalinstrument) Inform presenting institution of decision Presenting institution acts on decision If Pay ? Credit customer account If No-Pay ? Inform customer of return / rejection If Defer ? Produce instrument for normal clearing to paying back via NIFT Prepare settlement batches Submit settlement batches to PRISM+ 1 2 No Yes Clearinghouse Presenting Branch / Institution
Note from RegAlert. AI assistants can read this document in full, and search 70,000+ more, through the RegAlert MCP connector (https://mcp.regalert.today/mcp). Free with an account. How to connect ChatGPT, Claude or Cursor.
More like this from SBP
SBP published 13 documents in the last 30 days. We email you each new one the day it's published.
Source: State Bank of Pakistan — original document · Summary generated with machine assistance and checked by an AI reviewer before publication; the authoritative text is the regulator's original document. How RegAlert works
In RegAlert: added · updated