Rule · BB · 4 Oct 2015

PSD Circular Letter No. 10 : Revised implementation timeline for BD-RTGS System

The System Integration Testing (SIT) completion timeline for the BD-RTGS System is extended from October 1 to October 15, 2015, and the Go Live date is revised to October 22, 2015. This adjustment applies to all scheduled banks in Bangladesh, which are requested to take necessary steps to prepare for the go-live operation of the BD-RTGS system.

BangladeshBangladesh Bank

Lineage: In force

PSD Circular No. 2 dated 2015-0…PSD Circular No. 2 dated 2015-04-06PSD Circular Letter No. 10 :Revised implementation timeli…2015-10-04 · this documentPSD Circular Letter No. 10 : Revised implementation timeline for BD-RTGS System (2015-10-04)
amendssupersedesissued underrefers toproposed or not in RegAlertarrows run from the older text to the one that changes it

Similar documents from other regulators

More like this from BB

We email you every new BB publication the day it's published.

Source: Bangladesh Bank — original document · Summary generated with machine assistance and reviewed before publication; the authoritative text is the regulator's original document. How RegAlert works

In RegAlert: added · updated