Rule · BB · 17 Jun 2020
The Operating Guidelines for the JICA assisted Urban Building Safety Project are amended to replace the eligible geographical locations of Dhaka District, Gazipur District, Narayanganj District and Chittagong City with Dhaka District, Gazipur District, Narayanganj District and Chattogram District. Additionally, the previous Application form for Financing under the project is replaced by a modified form attached to the circular. These changes apply to all accredited Primary Financial Institutions under the project.
SME & S pecial Programmes Department
JICA-PIU(UBSP)
SMESPD Circular Letter No. 04 Date: 17 June 2020 CEO/MDs All accredited PFIs under Urban Building Safety Project Head Office, Dhaka. Dear Sirs, Regarding addendum of Operating Guidelines for JICA assisted Urban Building Safety Project (UBSP, BD-P84) Please refer to our SMESPD Circular no. 03/2016 dated 25 September 2016, the Operating Guidelines of UBSP project attached with the circular and SMESPD Circular Letter no. 03/2018 dated 07 November 2018. With the aim of extending financial support for safe working environment of RMG sector and smooth implementation of the project necessary amendments in the Operating Guidelines has been made. Details are explained below:
Attachment: As mentioned above
Sincerely Yours,
Md. Sharafat Ullah Khan
Project Director & Deputy General Manager
Phone: 9530331
Application for financing under Urban Building Safety Project (UBSP) funded by JICA Please affix First A. Organization Information Owner’s PP size Photograph
1. Name of the Organization/Company: …………………………………………....
2. Status of the company:
Proprietorship Partnership Joint Venture Private Limited
3. Year of Establishment: …………………….………………………………………………………………..
4. Main Products: ………………………………………………………………………………………………
5. Main Clients: …………………………………………………………………………………………………
6. Name of CEO: …………………………………….………………………………………………………….
7. Share Holders/ Directors:
SL No. Name of Share Holders Designation % o f Sh a re B. Factory/Building Information
1. Name of the Factory: ……………………….……….……….……………….……….………….………….
a) Name of the Building (Applied for): ……………………….……….……….……………….………….. b) Purpose of Loan:
Retrofitting Rebuilding Relocation Fire Safety New Construction c) Total Seeking Amount of Loan: ……………………….……….……….………………………….…….. (In Words): ……………………….……….……….……………………………………….………….…..
2. BGMEA/BKMEA/BGAPMEA Membership No: …………………………………….………….….……..
3. Address: ……………………….……….……….……………….……….…………………….………….….
……………………….……….……….……………….……….………………………………….……….…..
Tel. No (Office): …………………………….…………. (Residence): ………………………………....…. Fax: ………………………….……… Cell No: ……………………… E-mail: ………………………...….
4. Contact person: ……………………………………………… Cell No: ……………………………….…..
5. Availability of drawings and documents (as attachment):
Approved Plan Architectural Design Soil Test Report Structural Design Electrical Design Fire Safety Design
6. Name and address of Design Organization:
a) Architectural: …………………………………………………………………………………………….. b) Structural: ………………………………………………………………………………………………... c) Electrical: ………………………………………………………………………………………………… d) Fire Safety: ………………………………………………………………………………………………..
7. Name and address of Soil Testing Firm: ………………………………………………….………………...
……………………………………………………………………… IEB No: ……………………………………
8. Name of Designer:
a) Architectural: …………………………………………………………… IAB No: ……………………. b) Structural: ……………………………………………….……………… IEB No: …………………….. c) Electrical: ………………………………………………………………... IEB No: ……………………. d) Fire Safety: ………………………………………………………IAB & IEB No: …………………….. (Note: Resume of Structural Designer must be attached mentioning detail work experience)
9. Name and address of construction firm (if applicable): …………………………………………………..
…………………………………………………………………………………………………………………
10. Name of Supervising Engineer (if applicable): …………………………………… IEB No: …………….
11. Test Results of Materials during Construction (as attachment) (if applicable):
Concrete Re-bar Others
12. Plan approved by (Name of the Authority): ………………………………………………………………..
Memo No: …………………………………………………………………… Date: ………………..........
13. Approved for: ……………… storied; Construction completed (up to): ……………… floor
14. Floor Area (as per approved drawing):
a) Per Floor: …………………………… s qft b) Total: …………………………… s qft
15. Type of Building:
RCC frame structure Brick wall/ foundation Steel structure
16. Ownership: Self-Owned Rental
17. Number of Workers: a) Male: ……………………… b) Female: ………………………
18. Compliance Certificates from:
a) …………………………………… b) …………………………………… c) …………………………………… d) ……………………………………
19. Other Attachment (if any):
a) …………………………………… b) …………………………………… c) ……… …………………………… d) …………………………………… e) …………………………………… f) …………………………………… I hereby certify the correctness of figures/data/information and documents furnished herein/herewith. I also hereby undertake to furnish further particulars as may be required by the Authority and abide by the rules, regulations and instructions issued by PWD-PIU and BB-PIU of Urban Building Safety Project (UBSP). Management reserves the right to sanction/ reject the loan based on assessment. Signature of the Applicant:
Date:
Note from RegAlert. AI assistants can read this document in full, and search 70,000+ more, through the RegAlert MCP connector (https://mcp.regalert.today/mcp). Free with an account. How to connect ChatGPT, Claude or Cursor.
RegAlert holds no document that amends or replaces this one. This is not a check that it is in force: confirm with the regulator.
“and SMESPD Circular Letter no. 03/2018 dated 07 November 2018.”
“Please refer to our SMESPD Circular no. 03/2016 dated 25 September 2016”
More like this from BB
We email you every new BB publication the day it's published.
Source: Bangladesh Bank — original document · Summary generated with machine assistance and reviewed before publication; the authoritative text is the regulator's original document. How RegAlert works
In RegAlert: added · updated