Rule · SAMA · 27 Feb 2017 · 381000058504
Member Organizations must conduct a gap assessment and submit a compliance roadmap to the Institution by May 2017. They must provide quarterly reports until full compliance is achieved by January 2018. Organizations must define, approve, and maintain BCM governance, strategy, policy, BIA, BCP, DRP, and crisis management plans. Annual testing of BCP and DRP is required, with detailed results documented.
General Directorate of Bank Supervision
9041059769
Ref: 381000058504
Date: 01/06/1438
Attachments: 14
Circular
Respected,
Subject: Regulatory Guide for Business Continuity Management in the Banking Sector.
Starting from the Institution's keenness to improve the level of practices regarding business continuity planning in the event of incidents or disasters - God forbid - through having an effective, applied, and tested mechanism in the Bank/Financial Institution based on the best solutions and practices that provide a mature environment to ensure business continuity without interruption of important services and disruption of business, we inform you of the Institution's development and issuance of a regulatory guide for Business Continuity Management for the Banking Sector (attached), which the Bank/Financial Institution must fully comply with by following the following procedures:
First: Conduct a current status assessment of business continuity in the Bank compared to the requirements stated in the Regulatory Guide (Gap Assessment) to identify weaknesses in the Bank, with a plan of action (Roadmap) to comply with the Institution's requirements after assessing the current status and sending it to the Institution by no later than the end of May 2017.
Second: Provide the Institution with quarterly reports starting from the end of the second quarter until the Bank completes the Institution's requirements.
Third: Full compliance with applying all requirements stated in the Guide by the end of January 2018.
The Institution
P.O. Box 2992, Riyadh 11169, Telegrams Center, Telex 404400, Tel 4662525, Fax 4662671
General Directorate of Bank Supervision
Date:
Signatures:
Ref:
Attachments:
In case of any inquiries regarding this matter, you can contact the Manager of the Bank Information Feeding Risks Department, Mr. Marwan bin Hamad Al-Luhaidan, phone number (146330000) extension (5818) and email maalohaidan@SAMA.GOV.SA or Mr. Rashid bin Sulaiman Al-Rashid, phone number (146330000) extension (5591) and email Ralrasheed@SAMA.GOV.SA.
And accept my regards...
The Institution
Ahmed bin Abdullah Al Sheikh
Deputy Governor for Supervision
Distribution List:
Banks/Financial Institutions operating in the Kingdom of Saudi Arabia
P.O. Box 2992, Riyadh 11169, Telegrams Center, Telex 404400, Tel 4662525, Fax 4662671
Business Continuity Management Framework
February 2017
Version 1.0
Version 1.0
1.1 Introduction to the BCM Framework ......................................................... 3
1.2 Definitions ............................................................................................. 3
1.3 Scope ................................................................................................... 3
1.4 Applicability ......................................................................................... 3
1.5 Responsibilities ................................................................................... 4
1.6 Interpretation ...................................................................................... 4
1.7 Target Audience ................................................................................. 4
1.8 Review, Changes and Maintenance .................................................... 4
1.9 Reading Guide ..................................................................................... 4
2 Business Continuity Requirements ....................................................... 5
2.1 BCM Governance ............................................................................... 5
2.2 BCM Strategy ..................................................................................... 5
2.3 Business Continuity Policy ................................................................. 6
2.4 Business Impact Analysis (BIA) and Risk Assessment (RA) .............. 6
2.5 Business Continuity Plan (BCP) .......................................................... 7
2.6 IT Disaster Recovery Plan (DRP) ....................................................... 8
2.7 Cyber Resilience ............................................................................... 9
2.8 Crisis Management Plan ................................................................. 10
2.9 Testing ............................................................................................ 11
2.9.1 BCP testing .............................................................................. 11
2.9.2 DRP testing ............................................................................. 11
2.9.3 Executed tests ......................................................................... 11
2.10 Awareness and training ................................................................. 12
2.11 Communication ............................................................................. 12
2.12 Periodic Documents Review ........................................................... 13
2.13 Assurance ..................................................................................... 13
Version 1.0
Considering the need of 24 x 7 availability of the business operations by financial institutions in the Kingdom of Saudi Arabia, SAMA has developed a Business Continuity Management (BCM) framework for member organizations that would enhance the organizational resilience capability to ensure continuity and availability of their operations and services. The requirements are based on SAMA requirements, industry practices and international standards, such as ISO 22301, ISO 27001, Good practice guidelines from BCI, and Professional practice guidelines from DRII. All Member Organizations are required to comply with these requirements and integrate it formally in their BCM program.
The BCM framework document defines principles, objectives and control considerations for initiating, implementing, maintaining, monitoring and improving business continuity controls in member organizations. The BCM framework document is applicable to the full scope of the Member Organization, including subsidiaries, employees, subcontractors, third-parties and customers. The BCM framework document has an interrelationship with other corporate policies for related areas, such as enterprise risk management, health, safety and environment (HSE), physical security, cybersecurity (including cyber resilience and incident management).
The BCM Framework document is applicable to following:
Version 1.0
SAMA mandates the BCM framework requirements document to Member Organizations. This document outlines the BCM requirements to be implemented by the Member Organizations. SAMA is the owner and is responsible for periodically updating the BCM Framework document. The Member Organizations are responsible for adopting and implementing the requirements stated in this framework document.
SAMA, as the owner of the BCM framework requirements document, will provide interpretations of the principles, objectives and control considerations, if required.
This document is intended for board of directors, CEOs, chief risk officer, senior and executive management, business owners, owners of information assets, CIOs, CISOs, business continuity managers, internal auditors and for those, who are responsible for and involved in defining, implementing and reviewing business continuity controls.
This document will be reviewed and maintained by SAMA. SAMA will review this document periodically to determine its effectiveness, including the effectiveness of the framework to address emerging business continuity threats and risks. If applicable, SAMA will update this document based on the outcome of the review.
If a Member Organization considers that an update to this document is required, the Member Organization should formally submit the requested update to SAMA after obtaining approval from the business continuity manager and business continuity steering committee within the Member Organization. SAMA will review the requested update, and when approved, this document will be updated.
Version control will be implemented for maintaining this document. Whenever any changes are made, the preceding version should be retired and the new version should be published and communicated to all Member Organizations.
The BCM Framework represents the actual BCM domains and subdomains, principles, objectives, and control considerations.
The business continuity governance framework should be defined, approved, implemented and maintained, which should be monitored by senior management. The business continuity structure should be defined and communicated to all relevant employees and third parties.
To direct, control and evaluate the overall approach to business continuity within the Member Organization
A business continuity strategy should be defined and aligned with the Member Organization’s overall strategic business objectives.
To ensure that business continuity initiatives are in alignment with the strategic business objectives and embeds BCM as part of the good management practice within the Member Organization, in order to continual improvement in maturity.
A business continuity policy should be defined, approved and communicated to relevant stakeholders.
To document the Member Organization’s commitment and objective of the business continuity program, and to communicate this to the relevant stakeholders.
The Member Organization should perform a business impact analysis and risk assessment for all relevant activities to determine the business continuity, and disaster recovery requirements and improvements.
To ensure that each Member Organization has identified and prioritized their business processes along with key dependencies, and identified adequate controls in order to fulfill their business, regulatory, legal and compliance requirements with regards to business continuity
The Member Organization should define, approve and implement BCP for their critical activities. The compliance with BCP should be monitored, and the effectiveness should be measured and periodically evaluated.
The Member Organization should define, approve, implement and maintain a IT DRP for its critical activities and related technology infrastructure.
To ensure the Member Organization has IT DRP and up-to-date list of critical activities in place, in case of a disruptive incident
The Member Organization should ensure that critical services, business functions and processes run on reliable and robust infrastructure and software.
To ensure each that the Member Organization's critical services, business functions and processes are available when required and resistant to disruptions.
Note. For more control considerations to improve the overall resilience, e.g., threat management, vulnerability management, please refer to the SAMA - Cyber Security Framework.
The Member Organization should define, approve and implement a crisis management plan that would facilitate a well-managed response for major incidents, including rapid communication to ensure overall safety to both internal and external stakeholders.
To ensure the Member Organization has effective crisis management plan in place and up-to-date for critical member organization products, services, business functions and processes, in case of a disruptive incident.
The Member Organization should define, approve, implement, execute and monitor regular BCP and DRP tests to train their employees and third-parties and test the effectiveness of the BC and DR plans.
To ensure that the Member Organization’s existing BCP and DRP do work as defined and employees and third-parties are trained to execute these plans.
Detailed results of all exercises and tests should be documented for future reference. The exercises/tests results should include, but not be limited to the following considerations:
a. Confirm meeting the objectives of the exercised plan b. Confirm capabilities and readiness of recovery resources
c. Document lessons learnt and the required improvements
d. In case of failure, Capture the root-cause of the failure and remediation actions should be tracked to successful conclusion
Re-testing of the plan within the defined timelines in case of a failure, the timelines should not exceed the limit of three (3) months.
The Internal Audit of the Member Organization, or a qualified external auditor, should observe the business continuity and disaster recovery testing activities as an independent participant in order to provide a reasonable assurance on the executed activities, test results and to observe if the executed tests are meeting the Member Organization’s overall Business Continuity program objectives.
All BCP and DRP tests results should be reported to the BCM committee, senior management and the board of directors.
2.10 Awareness and training
Principle
The Member Organization should establish, implement and maintain a training and awareness program that effectively supports the BCM objectives by developing the required competency among staff.
Objective
The Member Organization should ensure BCM integration into its day-to-day activities, through an ongoing awareness plan, which should be documented.
Control considerations
2.11 Communication
Principle
The Member Organization should define, establish and maintain a communication process for periodic communications with SAMA on matters related to its BCM program.
Objective
To ensure that continuous communication is maintained with SAMA by defining, agreeing and adhering to communication protocol, frequency, and roles and responsibilities for communications
Control considerations
2.12 Periodic Documents Review
Principle
The business continuity and disaster recovery program, policies, plans and procedures should be reviewed and updated periodically, and in case of (major) change in the Member Organization’s critical products, services, business functions and/or processes.
Objective
To ensure that all the business continuity documents are up to date and can be used during a disruptive incident to recover the business operations.
Control considerations
2.13 Assurance
Principle
The BCM of the Member Organizations should be subjected to periodically reviews and audits by a qualified independent internal or external party to ensure its effectiveness, and to obtain assurance regarding the compliance with the SAMA BCM.
Objective
To ensure that an independent party is reviewing the BCM framework activities and reporting the identified issues to the senior management independently.
Control considerations
Note from RegAlert. AI assistants can read this document in full, and search 70,000+ more, through the RegAlert MCP connector (https://mcp.regalert.today/mcp). Free with an account. How to connect ChatGPT, Claude or Cursor.
RegAlert holds no document that amends or replaces this one. This is not a check that it is in force: confirm with the regulator.
“A Trade Repository must comply with SAMA Business Continuity Framework issued via SAMA circular 381000058504 dated 01/06/1438 H”
“A Trade Repository must comply with SAMA Business Continuity Framework issued via SAMA circular 381000058504 dated 01/06/1438 H”
“In continuation of Saudi Central Bank Circular No. 381000058504 dated 1438/6/1H, which issued the Regulatory Guide for Business Continuity Management in the Banking Sector”
More like this from SAMA
We email you every new SAMA publication the day it's published.
Source: Saudi Central Bank — original document · Summary generated with machine assistance and reviewed before publication; the authoritative text is the regulator's original document. How RegAlert works
In RegAlert: added · updated