Rule · SAMA · 19 May 2021

Providing Backup Generators in Branches and Transfer Centers

Local banks and financial institutions in the Kingdom must ensure branch service continuity by maintaining operational backup generators, verifying capacity, and conducting periodic tests. They must coordinate with the Saudi Electricity Company to prioritize main and backup data centers and headquarters for power support. Effective 2022/1/1G, institutions must submit an inventory of branches to be equipped with generators and a dedicated timeline to the Saudi Central Bank within three months.

Saudi ArabiaSaudi Central Bank
Annotations and obligations
5 obligations · 2 definitions
  • Obligation 5
  • Definition / condition 2
  • background, boilerplate

Lineage: No known changes

RegAlert holds no document that amends or replaces this one. This is not a check that it is in force: confirm with the regulator.

Mentions (1)a document this one mentionsopen the list below the graph ▾Mentions (1): a document this one mentions without changing it — open the list below the graphProviding Backup Generators inBranches and Transfer Centers2021-05-19 · this documentProviding Backup Generators in Branches and Transfer Centers (2021-05-19)
amendssupersedesissued underrefers todashed card: not in RegAlert (or proposed)arrows run from the older text to the one that changes it
Mentions (1): 1 document this one mentions without changing it
Refers to
  • “In continuation of Saudi Central Bank Circular No. 381000058504 dated 1438/6/1H, which issued the Regulatory Guide for Business Continuity Management in the Banking Sector”

Similar documents from other regulators

More like this from SAMA

We email you every new SAMA publication the day it's published.

Source: Saudi Central Bank — original document · Summary generated with machine assistance and reviewed before publication; the authoritative text is the regulator's original document. How RegAlert works

In RegAlert: added · updated