S1 institutions must implement recovery and resolution planning and submit the Organized Exit and Recovery Plan (PRSO) to the Central Bank of Brazil. They must maintain management information systems for accurate data, including IT asset inventories and critical service provider lists, and establish monitoring programs with critical levels for risk indicators. Institutions must predict comprehensive recovery and resolution strategies, continuously assess their own recovery capacity and resolvability, and maintain an Action Plan to eliminate barriers.

BrazilBanco Central do Brasil
Annotations and obligations
114 obligations · 51 definitions
  • Obligation 114
  • Definition / condition 51
  • background, boilerplate

Lineage: No known changes

RegAlert holds no document that amends or replaces this one. This is not a check that it is in force: confirm with the regulator.

Lei nº 6.099, de 12 de setembro de1974 — Dispõe sobre o tratamento …1974 · BR-LAWLei nº 6.099, de 12 de setembro de 1974 — Dispõe sobre o tratamento tributário das operações de arrendamento mercantil e dá outras providências (Law No. 6,099 of 12 September 1974 — tax treatment of financial leasing (arrendamento mercantil) operations) (1974-09-12)Lei nº 10.194, de 14 de fevereirode 2001 — Dispõe sobre a institui…2001 · BR-LAWLei nº 10.194, de 14 de fevereiro de 2001 — Dispõe sobre a instituição de sociedades de crédito ao microempreendedor, altera dispositivos das Leis nos 6.404, 8.029 e 8.934, e dá outras providências (Law No. 10,194 of 14 February 2001 on the establishment of microentrepreneur credit companies, amending Laws 6,404, 8,029 and 8,934) (2001-02-14)Law No. 12,865, of October 9, 2013— payment arrangements and paymen…2013 · BR-LAWLaw No. 12,865, of October 9, 2013 — payment arrangements and payment institutions that are part of the Brazilian Payment System (2013-10-09)+4 moresee all below the graph+4 moreResolution CMN No. 4502 —Establishes Minimum Requirements …2016 · BCBResolution CMN No. 4502 — Establishes Minimum Requirements for the Preparation and Execution of Recovery Plans by Financial Institutions (2016-06-30)Resolution CMN No. 4557 —Establishes the Risk Management S…2017 · BCBResolution CMN No. 4557 — Establishes the Risk Management Structure and Capital Management Structure (2017-02-23)CMN Resolution No. 4704 AmendingResolutions No. 4,193 and No. 4,5…2018 · BCBCMN Resolution No. 4704 Amending Resolutions No. 4,193 and No. 4,502 on Minimum Reference Equity, Level I, and Principal Capital Requirements (2018-12-19)Mentions (1)a document this one mentionsopen the list below the graph ▾Mentions (1): a document this one mentions without changing it — open the list below the graphCMN Resolution No. 5,187 —Recovery and Resolution Plann…2024-11-28 · this documentCMN Resolution No. 5,187 — Recovery and Resolution Planning Process for Financial Institutions (2024-11-28)Mentions (1)a document that mentions itopen the list below the graph ▾Mentions (1): a document that mentions it without changing it — open the list below the graphBCB Resolution No. 440 — Recoveryand Resolution Planning for Payme…2024 · BCBBCB Resolution No. 440 — Recovery and Resolution Planning for Payment Institutions and the Recovery and Organized Exit Plan (PRSO) (2024-11-28)Central Bank of Brazil InstructionNormative No. 573 — Establishes t…2024 · BCBCentral Bank of Brazil Instruction Normative No. 573 — Establishes the Submission Date for the First Organized Recovery and Orderly Exit Plan (PRSO) (2024-12-20)
amendssupersedesissued underrefers todashed card: not in RegAlert (or proposed)arrows run from the older text to the one that changes it
The links and the sentences they come from (12)
Supersedes
Amends
Issued under
+1 more
Basis for
Mentions (2): 1 document this one mentions and 1 document that mentions it, without changing it
Refers to
Referred to by

What changed in the obligations

Against Resolution CMN No. 4502 — Establishes Minimum Requirements for the Preparation and Execution of Recovery Plans by Financial Institutions (2016-06-30)

44 new obligations · 1 changed obligation · 1 change of scope · 1 change of who is bound · 30 not carried over

50 obligations are the same in both texts.

Changed (3)
  • Scope
    Before
    The preparation and revision of the recovery plan must be integrated into the institution's information management, risk management, capital management, and crisis management processes, as well as contingency and capital plans.
    Now
    Article 5. Recovery and resolution planning must be integrated into information management, risk management, and capital processes.
  • What must be done
    Before
    § 2. With a view to testing the adequacy of the critical levels defined in the monitoring program, the feasibility, and the effectiveness of recovery strategies, stress scenarios must include the hypothesis of the unviability of the institution's business model.
    Now
    Stress scenarios must be relevant to test the adequacy of critical levels defined in the monitoring program, the viability, and the effectiveness of recovery and resolution strategies.
  • Who is bound
    Before
    The executive board and the board of directors, if applicable, are responsible for the adoption of the strategies provided for in the recovery plan.
    Now
    Article 19. The board of directors and the board of directors, if any, are responsible for adopting the strategies provided for in the PRSO, except those executed under a resolution regime.
New in this text (44)
  • Article 2. Institutions that meet the criteria provided for in specific regulation for classification in Segment 1 – S1 must: I - implement recovery and resolution planning to respond to scenarios that compromise their viability; and
  • Article 2. Institutions that meet the criteria provided for in specific regulation for classification in Segment 1 – S1 must: II - prepare and submit to the Central Bank of Brazil the Organized Exit and Recovery Plan – PRSO.
  • Recovery and resolution planning presupposes the existence of: I - management information systems aligned with strategies and planned measures; and
  • Article 6. The institution must have management information systems capable of providing accurate and timely information, during normal operational periods and crisis periods, including during the course of a resolution regime eventually decreed, within the prudential conglomerate and the entities … I - to assess the value of business units and relevant entities, regarding which a strategy of ali…
  • II - to identify the operational and financial interconnections existing between entities covered by the scope of recovery and resolution planning, including interconnections related to: a) sharing of support services, personnel, and support infrastructure; and
  • II - to identify the operational and financial interconnections existing between entities covered by the scope of recovery and resolution planning, including interconnections related to: b) provision of guarantees and exposures resulting from transactions between related parties, in Brazil and abroad.
  • Article 6. The institution must have management information systems capable of providing accurate and timely information, during normal operational periods and crisis periods, including during the course of a resolution regime eventually decreed, within the prudential conglomerate and the entities … § 1. The institution must perform, within its own programming or if so determined by the Central B…
  • Article 6. The institution must have management information systems capable of providing accurate and timely information, during normal operational periods and crisis periods, including during the course of a resolution regime eventually decreed, within the prudential conglomerate and the entities … § 2. The institution must be capable of performing, based on the information referred to in item I…
  • Article 6. The institution must have management information systems capable of providing accurate and timely information, during normal operational periods and crisis periods, including during the course of a resolution regime eventually decreed, within the prudential conglomerate and the entities … I - inventory of information technology – IT assets highlighting the main computerized systems tha…
  • Article 6. The institution must have management information systems capable of providing accurate and timely information, during normal operational periods and crisis periods, including during the course of a resolution regime eventually decreed, within the prudential conglomerate and the entities … II - list of administrators of the entities covered by the scope of recovery and resolution planni…
  • Article 6. The institution must have management information systems capable of providing accurate and timely information, during normal operational periods and crisis periods, including during the course of a resolution regime eventually decreed, within the prudential conglomerate and the entities … III - data supporting the identification and assessment of critical functions;
  • Article 6. The institution must have management information systems capable of providing accurate and timely information, during normal operational periods and crisis periods, including during the course of a resolution regime eventually decreed, within the prudential conglomerate and the entities … IV - description of the methods and processes involved in the assessment of assets, business units…
  • Article 6. The institution must have management information systems capable of providing accurate and timely information, during normal operational periods and crisis periods, including during the course of a resolution regime eventually decreed, within the prudential conglomerate and the entities … V - assets that can be offered as collateral to obtain liquidity financing, either through liquidi…
  • Article 6. The institution must have management information systems capable of providing accurate and timely information, during normal operational periods and crisis periods, including during the course of a resolution regime eventually decreed, within the prudential conglomerate and the entities … VI - liabilities that can be reduced, extinguished, or converted into shares, for purposes of abso…
  • Article 6. The institution must have management information systems capable of providing accurate and timely information, during normal operational periods and crisis periods, including during the course of a resolution regime eventually decreed, within the prudential conglomerate and the entities … § 4. Internal audit, in its assessment of the reliability, effectiveness, and integrity of managem…
  • Article 8. Recovery planning must be guided by the preservation of the institution's viability, and resolution planning by the operational continuity of its critical functions.
  • Recovery and resolution planning comprises: II - the definition of strategies to address potential recovery and resolution situations; and
  • Recovery and resolution planning comprises: III - the self-assessment of recovery capacity and resolvability.
  • Article 13. The institution must predict a comprehensive set of resolution strategies, in response to different stress scenarios leading to resolution, with a view to ensuring the operational continuity of its critical functions.
  • § 1. The definition of resolution strategies must consider the assessment, at a minimum, of the following measures and their adoption before or during the course of a resolution regime:
  • III - transfer of assets and liabilities;
  • V - expropriation of share capital shares.
  • § 2. The institution must assess the viability of each strategy and indicate the preferred one.
  • Article 14. In order to preserve the continuity of critical functions performed by entities covered by the scope of recovery and resolution planning, the institution must be able to ensure the continuity of critical services in the context of the materialization of scenarios leading to recovery or resolution.
  • § 1. Service level agreements formalized for the provision of critical services must provide for the continuity of the supply of these services in the context of the materialization of scenarios leading to resolution, including after the event of the decree of a resolution regime.
  • § 2. Contracts signed with third-party providers of critical services must include specific clauses that:
  • I - prevent contract termination motivated exclusively by events of the decree of a resolution regime; and
  • II - facilitate the transfer of the contract to a transition institution or a definitive acquirer and guarantee the continuity of service provision for a period of not less than twelve months.
  • Article 15. The institution must maintain mechanisms and instruments to enable, at any time, its operations that may result in liquidation, central deposit, or registration in a financial market system or payment in a payment arrangement to be transferred to a transition institution or a definitive acquirer that is a participant of the same financial market system or payment arrangement.
  • Article 16. The institution must continuously perform the self-assessment of recovery capacity and resolvability, comprising, at a minimum, the following dimensions: I - data and information generation;
  • Article 16. The institution must continuously perform the self-assessment of recovery capacity and resolvability, comprising, at a minimum, the following dimensions: II - financial, in the context of the materialization of scenarios leading to recovery and resolution;
  • Article 16. The institution must continuously perform the self-assessment of recovery capacity and resolvability, comprising, at a minimum, the following dimensions: III - operational continuity of critical functions; and
  • Article 16. The institution must continuously perform the self-assessment of recovery capacity and resolvability, comprising, at a minimum, the following dimensions: IV - separability.
  • Article 17. The institution must prepare an Action Plan for Elimination or Mitigation of Barriers and Risks to Recovery and Resolution and adopt measures to eliminate or mitigate the barriers and risks identified in its self-assessment of recovery capacity and resolvability.
  • The plan and adoption of the measures mentioned in the caput must be included in the PRSO and have their execution monitored by internal audit.
  • Article 18. The board of directors and the board of directors, if any, must: V - ensure the effectiveness of the self-assessment process of recovery capacity and resolvability; and
  • Article 18. The board of directors and the board of directors, if any, must: VI - ensure the compatibility of the Action Plan for Elimination or Mitigation of Barriers and Risks to Recovery and Resolution with the institution's strategic planning and its timely execution.
  • Article 20. The PRSO, referred to in Article 2, caput, item II, must address: I - the organizational profile;
  • Article 20. The PRSO, referred to in Article 2, caput, item II, must address: II - the support structure;
  • Article 20. The PRSO, referred to in Article 2, caput, item II, must address: III - the governance of the recovery and resolution process;
  • Article 20. The PRSO, referred to in Article 2, caput, item II, must address: V - the self-assessment of recovery capacity and resolvability;
  • Article 20. The PRSO, referred to in Article 2, caput, item II, must address: VIII - other information established by the Central Bank of Brazil.
  • Article 20. The PRSO, referred to in Article 2, caput, item II, must address: § 1. The PRSO must report the results of the simulation exercises referred to in Article 6, § 1.
  • Article 20. The PRSO, referred to in Article 2, caput, item II, must address: § 3. The PRSO must be approved, prior to submission to the Central Bank of Brazil, by the board of directors and the board of directors, if any.
Not carried over (30)
  • Art. 4. The recovery plan must contain, at a minimum, a detailed description of the following items: I - critical functions and essential services performed by an entity included in the scope of the recovery plan;
  • Art. 4. The recovery plan must contain, at a minimum, a detailed description of the following items: VII - governance mechanisms as described in Articles 17 to 22.
  • Art. 7. The monitoring program must provide for the monitoring of the following items, at a minimum: I - indicators that demonstrate the actual or potential deterioration of the institution's capacity to meet its capital needs;
  • Art. 7. The monitoring program must provide for the monitoring of the following items, at a minimum: III - indicators that evidence the actual or potential variation in results or modifications in the pattern of revenue or expense sources;
  • Art. 7. The monitoring program must provide for the monitoring of the following items, at a minimum: IV - indicators that reflect the quality of active operations and their concentration in sectoral, geographic, and counterparty terms;
  • Art. 7. The monitoring program must provide for the monitoring of the following items, at a minimum: V - indicators that reflect the concentration of funding sources, their level of stability, and their costs;
  • Art. 7. The monitoring program must provide for the monitoring of the following items, at a minimum: VI - indicators and other information that signal activities or events that could significantly affect the image and operational or financial continuity; and
  • Art. 7. The monitoring program must provide for the monitoring of the following items, at a minimum: VII - indicators and other information that point to legal risks, contagion risks, and the effectiveness of internal controls.
  • Art. 8. The institution must establish adequate processes and systems for monitoring the indicators, critical levels, and other information contained in the monitoring program linked to the recovery plan.
  • The institution must evaluate the inclusion, at a minimum, of the following recovery strategies: VIII - maintenance of the supply of services provided by third parties, necessary for the operational continuity of the institution.
  • The recovery plan must contain the justification of the feasibility and analysis of the expected impact of the adoption of each recovery strategy individually and, where applicable, of the joint adoption of more than one strategy.
  • The justification of feasibility and impact analysis mentioned in the main text must evidence the time necessary for recovery strategies to produce effects and the expected costs and benefits.
  • The communication plan referred to in the main text must consider the relevance, adequacy, and timeliness of communication with stakeholders throughout the process of executing the recovery plan.
  • When submitting the recovery plan to the Central Bank of Brazil, in accordance with Article 23, item II, the institution must indicate the actions to be taken to eliminate or mitigate the barriers and risks mentioned in Article 15.
  • The deadlines associated with the adoption of the actions mentioned in the main text must be presented to the Central Bank of Brazil upon submission of the recovery plan.
  • The recovery plan must describe the governance mechanisms necessary for the execution of the recovery plan.
  • The recovery plan must be submitted for review by a unit of the institution independent of the areas responsible for its preparation.
  • The review provided for in the main text must: I - involve the evaluation of critical functions and essential services, the adequacy and robustness of the monitoring program and stress scenarios, the mapping of barriers and risks to the effectiveness of recovery strategies, governance, and other criteria and procedures associated with the operationalization of the plan; and
  • The review provided for in the main text must: II - be performed at least every three years, or whenever there is a relevant change in the economic-financial scenario, operating strategies, business model, organizational structure, or processes linked to the critical functions and essential services mentioned in item I of Article 4.
  • The recovery plan must be approved and revised by the executive board and the board of directors, if applicable, annually or whenever there is a relevant change in the economic-financial scenario, operating strategies, business model, organizational structure, or processes linked to critical functions and essential services.
  • The institutions mentioned in the main text of Article 2 and in Article 3 must: II - submit the recovery plans to the Central Bank of Brazil annually, or whenever there is a relevant change as provided in Article 20, within thirty days after their approval by the executive board and the board of directors, if applicable.
  • Institutions that cease to meet the criterion established are exempt from the obligations established in this Resolution: I - in the main text of Article 2 on three consecutive base dates; or
  • Institutions that cease to meet the criterion established are exempt from the obligations established in this Resolution: II - in Article 3, by evaluation of the Central Bank of Brazil.
  • The recovery plan of the institutions referred to in Article 2 must be submitted by December 31, 2017, observing the following schedule: I - by October 31, 2016: indication of the director responsible in accordance with item I of Article 23;
  • The recovery plan of the institutions referred to in Article 2 must be submitted by December 31, 2017, observing the following schedule: II - by December 31, 2016: presentation of the detailed description of the governance mechanisms in accordance with Article 17;
  • The recovery plan of the institutions referred to in Article 2 must be submitted by December 31, 2017, observing the following schedule: III - by March 31, 2017: presentation of the detailed description of the critical functions and essential services referred to in item I of Article 4;
  • The recovery plan of the institutions referred to in Article 2 must be submitted by December 31, 2017, observing the following schedule: IV - by June 30, 2017: presentation of the detailed description of the monitoring program and stress scenarios referred to, respectively, in items II and III of Article 4; and
  • The recovery plan of the institutions referred to in Article 2 must be submitted by December 31, 2017, observing the following schedule: V - by December 31, 2017: presentation of the detailed description of the recovery strategies and criteria and procedures for their operationalization; the communication plan; and the barriers and risks referred to, respectively, in items IV to VI of Article 4.
  • A financial institution that comes to meet the criterion established in the main text of Article 2 from January 1, 2017, must prepare and submit the recovery plan to the Central Bank of Brazil by December 31 of the year of inclusion.
  • § 2. The institution is exempt from including information it considers strategic in the description mentioned in the main text.

“Not carried over” means the sentence has no counterpart in this text; the rule can still be in force in another text.

Similar documents from other regulators

More like this from BCB

BCB published 10 documents in the last 30 days. We email you each new one the day it's published.

Source: Banco Central do Brasil — original document · Summary generated with machine assistance and reviewed before publication; the authoritative text is the regulator's original document. How RegAlert works

In RegAlert: added · updated